Toronto–York Spadina subway extension

The Toronto–York Spadina subway extension (TYSSE) is an extension of the Toronto subway's Line 1 Yonge–University which opened on December 17, 2017. It runs 8.6 kilometres (5.3 mi) northwest from the line's previous terminus at Sheppard West station serving six new stations and terminating at Vaughan Metropolitan Centre station near Jane Street and Highway 7 in Vaughan.[1][2] The TYSSE was the first new section of a Toronto subway line to be opened since the opening of Line 4 Sheppard in 2002.[3]

Toronto–York Spadina subway extension
York University station has the highest ridership on the extension
Overview
StatusOpen
LocaleToronto and Vaughan, Ontario
Stations6
Service
TypeRapid transit
SystemToronto subway
Operator(s)Toronto Transit Commission
History
OpenedDecember 17, 2017; 7 years ago (2017-12-17)
Technical
Line length8.6 km (5.3 mi)
CharacterUnderground
Track gauge4 ft 10+78 in (1,495 mm) Toronto gauge
Route map

Vaughan
Highway 407
Pioneer Village
York University
Finch West
Downsview Park
Sheppard West
To Finch via Union

Handicapped/disabled access All stations are accessible

The extension was first envisioned in the 1980s, though the route of an extension to York University was not finalized until 2005. Despite the lack of development there at the time, an extension to Vaughan was added and construction began in 2008. Initially expected to open in time for the 2015 Pan American Games, the extension went overbudget and opened two years after originally planned. The new stations were among the first to eliminate collector booths and Toronto TTC fares are charged at the Vaughan stations. Upon opening, most stations on the extension saw below average ridership compared to the rest of the subway system.

Background

edit

Line 1 Yonge–University (initially running almost exclusively along Yonge Street) opened in 1954 and has been extended several times. The first section of the line's western branch dates back to 1963 when an extension, named the University Subway, was built to curve north from Union Station below University Avenue and Queen's Park to near Bloor Street, where it turned west to terminate at St. George station at St. George and Bloor Streets. This extension opened on February 28 of that year.[4] In 1978, a further eight-stop extension, dubbed the Spadina Subway, opened, bringing the western leg to Wilson station in North York (then a borough separate from Toronto). In 1996, a short 2-kilometre (1.2 mi) one-stop extension to Downsview station (renamed Sheppard West in May 2017) opened.[5][6]

After the line reached Wilson, there were several proposals to extend the line farther. An extension into Vaughan had been suggested as early as 1988, when Vaughan mayor Lorna Jackson campaigned during the Vaughan municipal elections to extend the subway system to the proposed Highway 407 corridor.[7]

Yonge–Spadina loop plans

edit

In 1989, a proposal was put forward as part of the Network 2011 plan to construct a loop to join the Spadina and Yonge branches along the hydro corridor north of Finch Avenue to Finch station, where the Yonge branch terminates. However, officials from York University and York Region lobbied for the loop to run through the university campus and along Steeles Avenue instead as they felt it would better suit commuters.[8] In the early 1990s, the loop plan, known as the Yonge–Spadina Subway Loop Project, was discussed, with the option through York's campus being favoured. The western leg of the line would have been extended by three stations to York University in the first phase of the project while the portion east along Steeles Avenue and back south down Yonge Street to Finch station to close the loop would have been built in later phases.[9]

In 1992, as an interim project, construction began on the aforementioned 1996 extension of the Spadina line to Downsview station.[5] In 1994, an environmental assessment for the first phase of the loop project was completed, but the extension was not built due to lack of funding.[10] Despite this, lobbying by politicians to extend the line continued.[11]

Change of plans to an extension to Vaughan

edit

In 2000, the City of Vaughan again lobbied for a subway extension to their municipality as they planned to build a new city core (today's Vaughan Metropolitan Centre) at Highway 7 and Jane Street. This second lobbying effort was ultimately successful and led to the abandonment of the loop proposal.[8] During the proposal stage of this plan, the TTC had concluded there were insufficient projected population densities to justify the line north of Steeles Avenue, with some of the new stations projected to be among those with the lowest ridership of the subway system.[12] The preferred alignment and placement for four stations for the extension beyond Downsview station to Steeles (one station farther than what was planned in 1994) via York University were finalized in September 2005.[9][13] In March 2006, the provincial government announced $670 million in funding for the extension, with the caveat that the line would also be extended to serve the future Vaughan Metropolitan Centre.[14] At the time, the area around the mostly vacant VMC site was occupied by big-box stores and freeways, and lacked the dense development that surrounds most other subway stations.[15] The preferred alignment and placement for the two stations in York Region was finalized in 2008.[16]

The TTC board approved design principles for stations in 2006, before approving a station design philosophy in 2009. This included integrated design by architects, public art and stations to meet Toronto Green Standards.[17] Consultations on the detailed design of stations took place in 2009 and 2010.[18][19]

Greg Sorbara, former deputy premier of Ontario and finance minister, was a key promoter of the TYSSE to York University and into York Region, in which his riding was based. In his memoirs, he said that "it would not only be great for the people in the region, but also for my political prospects".[20] In 2015, Sorbara indicated that, while David Miller was mayor of Toronto, Miller was initially not enthusiastic about the extension. Sorbara said, "He should have been thrilled at the prospect of the province providing $670 million for more subway infrastructure, regardless of where it went."[20]

Temporary busway

edit

In 2003, a temporary busway was planned between Downsview (now Sheppard West) station and the campus, but was opposed by the university, which felt it would lessen government willingness to extend the subway. After numerous delays, construction on the York University Busway started on July 25, 2008,[21] with a short section of the busway opened on September 6, 2009[22] and the remainder opened on November 20, 2009.[23]

Construction

edit
 
Advertisement from September 2017 announcing the extension's December opening referencing Highway 407 and area code 416, referring to Toronto proper

The estimated cost was $2.09 billion in 2006, which have been escalated to $2.63 billion considering costs at the year of occurrence.[24] The Province of Ontario deposited $870 million into the Move Ontario Trust. The federal government committed $697 million.[25] The City of Toronto and the Regional Municipality of York committed to fund one-third of total project costs, with Toronto contributing $526 million and York Region contributing $352 million.[1][26]

The first construction contract was awarded on February 27, 2008.[27] Construction commenced in July 2008 with the relocation of sewers.[28] The official ground breaking ceremony was held on November 27, 2009, with a planned opening date of 2015.[26] The TTC purchased two tunnel boring machines in late 2010 from LOVAT Inc. (since acquired by Caterpillar Inc.) for $58.4 million to dig tunnels on this extension, and two more boring machines were delivered in early 2011.[29][30] Tunnel boring for the extension began on June 17, 2011[31] and was completed on November 8, 2013.[32] The TTC later reported that 1,400,000 cubic metres (49,000,000 cu ft) of material had been excavated, with over 54,000 concrete tunnel segments installed.[33]

In November 2014, the TTC indicated that the 2016 opening date would likely be missed, following poor performance by some contractors, death of a worker at the York University station site and harsh winter weather.[34][35] In March 2015, TTC CEO Andy Byford announced that the project was over budget, and that project management problems had resulted in the dismissal of two TTC managers.[36][37] Toronto City Council approved an additional $150 million in funding, with $90 million from Toronto and $60 million from York Region.[38] The TTC subsequently signed a contract with Bechtel, worth up to $80 million, to assume management of the last third of the construction.[39] This bypassed the tendering process usually used to hire contractors. The extension would open two years later than originally planned, in 2017.[40] In January 2016, it was announced that the project was $400 million over budget, to a total cost of $3.2 billion.[37]

In June 2016, trackwork was completed, with a ceremony attended by Premier of Ontario Kathleen Wynne and other dignitaries.[41] In spring 2017, the third rail which provides power to trains was turned on for the first time,[42] with the first test train running on the extension in April. In May 2017, Downsview station was renamed Sheppard West in preparation for the opening of the new Downsview Park station.[6] In September 2017, Byford announced that the extension would open in December 2017,[43] with the TTC running "ghost trains" to test the extension from November.[44]

The extension opened on December 17, 2017, with an opening ceremony attended by Prime Minister Justin Trudeau, Premier of Ontario Kathleen Wynne and Mayor of Toronto John Tory.[45][46]

Connecting infrastructure

edit

In addition to the subway line, other transit infrastructure was built as part of the TYSSE project. Downsview Park station is an interchange between the subway and the Barrie line – a regional rail line which is part of the GO Transit system. The station is fully integrated between the two modes.[47] Toronto Transit Commission bus terminals were built at Finch West and Pioneer Village stations and are integrated into the station buildings. York Region Transit (YRT) bus terminals were constructed at Pioneer Village and Vaughan Metropolitan Centre; however, these are located outside of the fare-paid areas, adjacent to but outside the stations. A GO Transit bus terminal (also used by YRT buses) was built at Highway 407 station, again outside the paid area, but within the main station building. This station was also designed to connect with the proposed Highway 407 Transitway.

Finch West was built with a knock-out panel that would allow for easier future construction of the Finch West LRT, then being planned[48] – construction of this light rail line began in 2019 and it is scheduled to open in 2024.[49]

Vaughan Metropolitan Centre is also an interchange between the subway and the Highway 7 Rapidway, used by YRT's Viva and Brampton Transit's Züm services. The bus rapid transit dedicated on-street right-of-way opened in conjunction with the subway, and there is direct escalator and elevator access connecting the station concourse with the covered rapidway stop.[50]

Paid commuter parking lots were built at Finch West (358 spaces), Pioneer Village (1,950 spaces) and Highway 407 (560 spaces) – parking was initially free until April 2018 as ridership grew on the line.[51] Passenger pick-up and drop-off facilities were also built at Finch West (10 spaces), Pioneer Village (11 spaces) and Highway 407 (30 spaces).[33] These are owned by the TTC and operated by the Toronto Parking Authority.[52] At Vaughan Metropolitan Centre, SmartCentres built a 900-space parking lot to serve the extension.[52]

Public art and architecture

edit
 
Spin by Panya Clark Espinal at Downsview Park station

Stations on the extension (in keeping with the pattern of the original Spadina line) feature distinct station architecture and public art.[17][53][54] TTC and City policy requires one percent of the budget to be spent on public art.[55] However, the platform walls have no tiles or other cladding and are simply bare concrete, though structural elements on the platforms themselves are clad, as is the case with much of the Line 4 Sheppard stations.[53] The interactive artwork at Pioneer Village has not been turned on due to concerns about displaying profanity, which would violate the 2009 revision of the TTC's by-law.[56]

Station Architect Public art
Downsview Park Aedas Spin by Panya Clark Espinal
Finch West Spadina Group Associates – All Design (architect Will Alsop) and IBI Group Bruce McLean
York University Foster + Partners Piston Effect by Jason Bruges Studio
Pioneer Village Spadina Group Associates – All Design (architect Will Alsop) and IBI Group LightSpell by Tim Edler and Jan Edler
Highway 407 Aedas Sky Ellipse by David Pearl
Vaughan Metropolitan Centre Grimshaw Architects Atmospheric Lens by Paul Raff Studio

Operating costs

edit

According to a TTC forecast reported by transit advocate Steve Munro in early 2015, the TTC's annual operating costs for the entire TYSSE would be $33.7 million, or $14.2 million net of revenue. This would produce a 58 percent cost recovery compared to 70 percent for the TTC system as a whole. These costs, including those for the portion in Vaughan, will be covered by the TTC and the City of Toronto.[57] In 2016, the expected net cost to run the extension was revised to $30 million.[58]

According to a 2008 memo of understanding between York Region and the City of Toronto:

The TTC will be responsible for the full operating costs of the Spadina subway extension from Downsview (renamed Sheppard West in May 2017) to the Vaughan Corporate Centre (renamed Vaughan Metropolitan Centre) and receive all revenue from the Project (passenger revenue, commuter parking, advertising, retail leasing), with the exception of the operating costs and revenues for bus terminals and passenger pickup and drop off facilities located within York Region, which shall be maintained and operated by York Region.[59]

Fares

edit

Fare policy within Vaughan

edit

Although Highway 407 and Vaughan Metropolitan Centre stations are located in Vaughan (within York Region) outside Toronto city limits, regular Toronto TTC fares are charged when entering or exiting these stations to simplify fare collection. This practice is in contrast to TTC-operated bus routes that cross the Toronto–York boundary at Steeles Avenue, where a second fare is charged. However, an additional fare is required for those paying by cash when transferring between the subway and suburban transit service providers, such as York Region Transit (YRT), at these stations, as is the case when transferring to other suburban transit services at stations within or bordering Toronto.

This is similar to the policy in 1968, when five subway stations opened outside the pre-1998 Toronto city limits in what was the TTC's "Zone 2" area at the time but no extra Zone 2 fare was required to reach those stations, whereas extra fare was charged to connect with suburban TTC bus routes in the boroughs of Metropolitan Toronto.[60][61]

Since February 26, 2024, free transfers between the TTC and all other GTA transit services (or discounted transfers with fare-by-distance GO Transit), have been available for customers paying by Presto cards or contactless credit or debit cards.[62]

Collector and legacy fare media phase-out

edit
 
Installed (but never used as such) collector booth at Highway 407 station. Note the customer service attendants.

The TYSSE stations were among the first to eliminate staffed fare collector booths, along with the sales of TTC's legacy fare media products – such as tokens – in favour of the Presto card. As a result, these stations opened with roaming customer service attendants, although collector booths had been installed per station plans.[63] Collector-booth closures at more stations along the west branch of the line, moving south from the TYSSE stations, followed later.[64][65]

Ridership numbers

edit

Early statistics published by CBC News report ridership numbers for three of six new stations on the TYSSE. In total, "57,100 riders boarded trains at the new stations during a week of service in May [2018]."[66] Finch West station pulled the most riders for the month, with approximately 17,000 customers using the station daily (for comparison, Lansdowne station on Line 2 Bloor-Danforth has similar usage).[67] It is worth noting that these numbers were recorded during York University's strike, leading to fewer passengers at Pioneer Village and York University. Downsview Park and Highway 407, despite both having direct connections to GO Transit, saw some of the worst ridership numbers in the entire subway system, with 2,000 daily customers at Downsview Park and 2,900 at Highway 407.[66] Since the opening of the extension to Vaughan, Downsview Park has replaced Bessarion as the least used subway station on the TTC.[67]

Statistics in late 2018 showed that ridership at Downsview Park increased to 2,500 customers per day and Highway 407 increased to 3,400. The busiest station on the extension is now York University, which has about 38,000 daily customers.[68] Finch West and Pioneer Village both serve approximately 17,000 customers and the terminus, Vaughan Metropolitan Centre, has a daily usage of 14,800. However, the average daily usage of all TTC subway stations is a little more than 34,000, which means that aside from York University station, all stations belonging to the extension are still seeing well below average usage.[69]

TTC ridership information from 2023 to 2024 showed that the average number of boardings per day was 5,600 at Downsview Park and 7,600 at Highway 407. This is approximately double compared to 2018 but still well below the Toronto subway average. Ridership at the other four stations on the extension ranged between 16,600 and 20,400, which is near the system median of 19,700.[70] The busiest stations on the extension are York University and Vaughan Metropolitan Centre, with around 20,400 daily riders.[70]

Development

edit
 
Vaughan Metropolitan Centre in 2022

The TYSSE has spurred the development of Vaughan's transit-oriented city centre at Vaughan Metropolitan Centre.[15] Vaughan Councillor Alan Shefman stated in 2016 that the new city centre will eventually create the density to justify a subway.[71] To this end, Vaughan Mayor Maurizio Bevilacqua worked with a developer to build several high-rise buildings near Vaughan Metropolitan Centre station; however, when the extension opened in December 2017, the area still mainly consisted of big box stores, low rise commercial buildings and parking lots.[12] By 2023, however, several high-density residential towers were scheduled to be completed in the area.[72] As a precedent, the Sheppard subway shows that while a subway may spur development, that development may not result into a high subway ridership.[73] The Toronto Star stated that commuter destinations may be scattered throughout the Greater Toronto Area where public transit is inconvenient to use.[74]

Outgoing TTC CEO Andy Byford said: "People say '[build] there and they will come.' I think the most pressing need is to now focus on subway expansion where it's not so much that they will come, it's [that] there's already a demonstrable need." However, Globe and Mail columnists wrote in the context of the TYSSE: "But that advice will have to compete with the growing power of the suburbs, and the eagerness of Queen's Park to court them." Toronto city councillor and TTC commissioner Glenn De Baeremaeker said: "Whether [the subway], quote, merits on a technical sense, the ridership or not, it's a philosophical decision the city has made and society has made. People like subways."[12]

Future

edit
 
A future extension of Line 1 could serve Canada's Wonderland, a major regional amusement park, on Major Mackenzie Drive.

York Region, in their 2022 Transportation Master Plan, proposed further extensions of Line 1 on both the University and Yonge legs.[75] One proposal was to extend Line 1 along Jane Street from Vaughan Metropolitan Centre station north to Major Mackenzie Drive West (adjacent to Cortellucci Vaughan Hospital and just north of Canada's Wonderland amusement park), with possible intermediate stations at Rutherford Road (adjacent to Vaughan Mills shopping mall) and Langstaff Road. The other proposal was to extend Line 1 along Yonge Street from the future High Tech station to Major Mackenzie Drive East (adjacent to Richmond Hill GO Station), with possible intermediate stations at Bantry Avenue and 16th Avenue / Carrville Road).

As of July 2024, these plans are not funded and are forecast for implementation in 2051 at the earliest. The York Region Rapid Transit Corporation endorsed these plans in their long-term rapid transit system map.[76]

References

edit
  1. ^ a b "TTC Spadina subway extension website". .ttc.ca. Archived from the original on October 25, 2012. Retrieved February 13, 2014.
  2. ^ "Justin Trudeau joins premier, mayor at TTC line 1 extension opening". CBC News. December 15, 2017. Retrieved September 16, 2023.
  3. ^ WSP. "Toronto-York Spadina Subway Extension". Retrieved July 24, 2024.
  4. ^ "2013 TTC Operating Statistics". Toronto Transit Commission. Archived from the original on July 25, 2021. Retrieved October 2, 2024.
  5. ^ a b Bow, James. "Downsview Station". Transit Toronto. Archived from the original on February 13, 2021. Retrieved March 15, 2020.
  6. ^ a b "Downsview station officially becomes Sheppard West". CBC News. May 7, 2017. Retrieved July 26, 2024.
  7. ^ "Vaughan". Toronto Star. November 8, 1988. Archived from the original on April 4, 2017.
  8. ^ a b Bow, James. "A Subway To York University And Beyond: The province proposes a belt line". Transit Toronto. Archived from the original on May 3, 2018. Retrieved May 2, 2018.
  9. ^ a b "Spadina Subway Extension – Downsview Station to Steeles Avenue Environmental Assessment" (PDF). VivaNext. Retrieved July 26, 2024.
  10. ^ "TTC Spadina Subway Extension | ontario.ca". www.ontario.ca. March 20, 2014. Retrieved July 26, 2024.
  11. ^ "Local politicians call for subway extension to York University". CBC News. November 16, 2000. Retrieved July 26, 2024.
  12. ^ a b c Moore, Oliver; Gray, Jeff (December 14, 2017). "Next stop, Vaughan: Inside the Toronto subway's big move beyond the city limits". The Globe and Mail. Archived from the original on December 15, 2017. Retrieved December 15, 2017.
  13. ^ "Spadina North extension preferred alignment". City of Toronto. February 12, 2012. Archived from the original on May 24, 2006. Retrieved February 17, 2012.
  14. ^ "Liberal budget heavy on money for transportation". CBC News. March 23, 2006. Archived from the original on June 1, 2008. Retrieved July 27, 2024. $670 million to extend TTC subway system to Vaughan, north of the city.
  15. ^ a b Javed, Noor (April 6, 2012). "Toronto's subway brings downtown vision to Vaughan". Toronto Star. Archived from the original on August 15, 2016. Retrieved June 30, 2016.
  16. ^ "A Subway To York University and Beyond - Transit Toronto - Content". transittoronto.ca. Retrieved July 27, 2024.
  17. ^ a b "Toronto-York Spadina Subway Extension Project - Station design philosophy" (PDF). Toronto Transit Commission. September 24, 2009. Retrieved July 27, 2024.
  18. ^ "Toronto-York Spadina Subway Extension Project - York University station Approval of conceptual design" (PDF). Toronto Transit Commission. September 24, 2009. Retrieved July 27, 2024.
  19. ^ "Toronto-York Spadina Subway Extension Project - York University station Approval of finishes and artwork" (PDF). Toronto Transit Commission. August 23, 2010. Retrieved July 27, 2024.
  20. ^ a b James, Royson (May 4, 2015). "Ours is to question why, and why again: James". Toronto Star. Archived from the original on August 4, 2016. Retrieved June 4, 2016.
  21. ^ Mackenzie, Robert (July 25, 2008). "Ground-breaking for York University busway project today". transittoronto.ca. Archived from the original on December 2, 2020. Retrieved February 17, 2012.
  22. ^ Mackenzie, Robert (September 5, 2009). "TTC revises routes and services, September 6: 196 York University Rocket". transittoronto.ca. Archived from the original on December 2, 2020. Retrieved February 17, 2012.
  23. ^ Mackenzie, Robert (November 14, 2009). "York University busway opens, November 20". transittoronto.ca. Archived from the original on December 2, 2020. Retrieved February 17, 2012.
  24. ^ TTC (March 26, 2008). "Toronto-York Spadina Subway Extension Project Delivery Strategy Process". Archived from the original on April 2, 2015. Retrieved March 6, 2015.
  25. ^ "Bus Rapid Transit Service Breaks Ground in Mississauga" (PDF). Metrolinx. Archived from the original (PDF) on July 17, 2016. Retrieved April 23, 2014.
  26. ^ a b "Toronto-York Spadina Subway Extension breaks ground". Railway Gazette. November 30, 2009. Archived from the original on October 8, 2012. Retrieved January 16, 2013.
  27. ^ "Spadina Subway Extension February 2008 Update". TTC. Retrieved March 31, 2008.
  28. ^ "Work begins on subway extension into York". CTV. July 9, 2008. Archived from the original on May 22, 2011. Retrieved July 11, 2008.
  29. ^ Mackenzie, Robert (August 8, 2009). "Extending the Spadina subway: Boring news". Transit Toronto. Archived from the original on December 2, 2020. Retrieved August 8, 2009.
  30. ^ "Major transit delay – Rapid transit project pushed back to 2020". Yorkregion.com. May 20, 2010. Archived from the original on March 6, 2012. Retrieved February 17, 2012.
  31. ^ "Tunnel boring for Toronto-York Spadina Subway Extension begins" Archived July 9, 2011, at the Wayback Machine TTC. June 17, 2011
  32. ^ ""TTC Project News December 2013"". Archived from the original on February 22, 2014. Retrieved February 13, 2014.
  33. ^ a b "Spadina Subway Extension". TTC. Retrieved October 20, 2024.
  34. ^ "Spadina subway extension may miss 2016 completion date". CBC News. November 5, 2014. Retrieved July 26, 2024.
  35. ^ Scallan, Niamh; Aulakh, Raveena (October 11, 2011). "Workers were trapped in their machines in deadly accident at TTC site". Toronto Star. Archived from the original on October 13, 2011. Retrieved October 12, 2011.
  36. ^ "TTC fires 2 managers linked to York subway expansion". CBC News. March 19, 2015. Retrieved July 26, 2017.
  37. ^ a b "Toronto-York Spadina subway extension $400M over budget". Canadian Broadcasting Corporation. January 15, 2016. Archived from the original on July 3, 2016. Retrieved June 4, 2016.
  38. ^ Powell, Betsy (March 31, 2015). "Council OKs $150-million deal to fix Spadina subway extension plan". Toronto Star. Archived from the original on May 18, 2015. Retrieved May 9, 2015.
  39. ^ Hui, Ann (April 13, 2015). "TTC hires firm to manage troubled Spadina subway extension". The Globe and Mail. Archived from the original on August 18, 2015. Retrieved May 9, 2015.
  40. ^ Wetselaar, Sean (April 13, 2015). "Bechtel awarded contract to manage completion of Spadina subway extension". Toronto Star. Retrieved July 26, 2024.
  41. ^ "Completion of trackwork for the Toronto-York Spadina Subway Extension". Toronto Transit Commission. June 6, 2016. Retrieved July 26, 2024.
  42. ^ "Line 1 extension powers up for TTC testing and trial runs". Toronto Transit Commission. March 27, 2017. Retrieved July 26, 2024.
  43. ^ Westoll, Nick (September 5, 2017). "Toronto-York Spadina Subway Extension scheduled to open in mid-December". Global News. Retrieved July 26, 2024.
  44. ^ Draaisma, Muriel (November 26, 2017). "'Ghost' trains running on new Line 1 extension as TTC tests $3.1B service". CBC News. Retrieved July 26, 2024.
  45. ^ "Justin Trudeau joins premier, mayor at TTC line 1 extension opening". CBC News. December 15, 2017. Retrieved September 16, 2023.
  46. ^ Beattie, Samantha; Spurr, Ben (December 16, 2017). "After delays, cost overruns, and tragedy, a subway to Vaughan is complete". Toronto Star. Retrieved July 26, 2024.
  47. ^ "More Barrie GO Trains". GO Transit. Archived from the original on December 13, 2017.
  48. ^ "Finch West LRT Project FAQs" (PDF). Metrolinx. 2019. Archived from the original (PDF) on November 28, 2022. Retrieved May 3, 2021.
  49. ^ "Toronto LRT woes: Finch West lawsuit underway, Eglinton Crosstown won't open before 2025". CityNews. October 2, 2024. Archived from the original on October 2, 2024.
  50. ^ "Changes are coming to Vaughan". Vivanext. Retrieved November 7, 2017.
  51. ^ Shum, David (April 23, 2018). "Commuter parking lots on Line 1 extension no longer free on weekdays - Toronto". Global News. Retrieved October 20, 2024.
  52. ^ a b "Paid parking will be available for subway riders at Vaughan station". yorkregion.com. November 29, 2017. Archived from the original on January 18, 2018. Retrieved January 17, 2018.
  53. ^ a b Dixon, Guy (September 29, 2017). "New stations of long-awaited TTC subway expansion integrate art into architecture". The Globe and Mail. Retrieved July 25, 2024.
  54. ^ Bloom, Jessica (December 21, 2017). "Take a look at the stunning public art in Toronto's new subway stations". Toronto Life. Retrieved July 25, 2024.
  55. ^ "Millions spent on art at 6 new TTC subway stations". CityNews Toronto. December 19, 2017. Retrieved July 25, 2024.
  56. ^ "Toronto subway art installation halted over profanity concerns". BBC News. January 4, 2018. Retrieved July 25, 2024.
  57. ^ Munro, Steve (March 2, 2015). "TTC 2015–2024 Capital Budget: System Expansion Projects". Archived from the original on July 2, 2016. Retrieved June 29, 2016.
  58. ^ Munro, Steve (November 1, 2016). "SmartTrack Plans Unravel: Munro". The Torontoist. Archived from the original on November 2, 2016. Retrieved November 3, 2016. The Spadina subway extension to Vaughan is expected to add $30 million (net) to the TTC's costs in coming years, but this number has only recently appeared in budget projections.
  59. ^ "Toronto-York Spadina Subway Extension Memo of Understanding – Operating and Maintenance Cost Responsibilities" (PDF). Toronto Transit Commission. June 18, 2008. Archived (PDF) from the original on August 16, 2016. Retrieved June 29, 2016.
  60. ^ James Bow. "A Subway to York University and Beyond: North of Finch". Transit Toronto. Archived from the original on September 11, 2019. Retrieved February 10, 2021.
  61. ^ "Line 1 extension opening brings TTC service changes". TTC. Archived from the original on November 3, 2021. Retrieved February 3, 2021.
  62. ^ "Ontario rolling out GTA-wide transit fare integration on Feb. 26". CBC News. February 6, 2024. Retrieved February 6, 2024.
  63. ^ "York University station – Site plan (P. 19)" (PDF). Toronto Transit Commission. Archived (PDF) from the original on November 26, 2020. Retrieved April 19, 2020.
  64. ^ "New Customer Service Agents at Yorkdale and Lawrence West stations". Toronto Transit Commission. January 6, 2019. Archived from the original on January 10, 2019. Retrieved June 15, 2019.
  65. ^ "New station model coming to 20 more subway stations". Toronto Transit Commission. Archived from the original on January 7, 2020. Retrieved January 6, 2020.
  66. ^ a b "New subway service is transforming Vaughan, but not all stations are busy, TTC figures show". CBC News. Archived from the original on October 23, 2018. Retrieved November 11, 2018.
  67. ^ a b "Toronto Transit Commission Subway ridership, 2018" (PDF). Toronto Transit Commission. Archived (PDF) from the original on January 26, 2019. Retrieved February 5, 2019.
  68. ^ "Subway ridership, 2019" (PDF). Toronto Transit Commission. Archived (PDF) from the original on November 28, 2022. Retrieved January 30, 2023. This table shows the typical number of customer-trips made on each subway on an average weekday and the typical number of customers travelling to and from each station platform on an average weekday.
  69. ^ "Two stations on new York subway extension among the least used on the TTC network". Toronto Star. December 16, 2018. Archived from the original on December 18, 2018. Retrieved December 23, 2018.
  70. ^ a b "Subway ridership, 2023-2024" (PDF). Toronto Transit Commission. Retrieved November 22, 2024. This table shows the typical number of customer-boardings made on each subway line and the number of customers travelling to and from each station platform on a typical weekday in Sep 2023-Aug 2024.
  71. ^ Kalinowski, Tess (March 3, 2016). "Vaughan councillor challenges Yonge subway 'no-capacity mythology'". Toronto Star. Archived from the original on August 5, 2016. Retrieved June 9, 2016.
  72. ^ "Groundbreaking Development in the VMC". Downtown Vaughan Metropolitan Centre. Archived from the original on May 13, 2021. Retrieved May 13, 2021.
  73. ^ Elliott, Matt (December 5, 2014). "Sheppard subway is a costly cautionary tale Toronto risks repeating". Metro News. Archived from the original on March 19, 2016. Retrieved December 5, 2014.
  74. ^ James, Royson (March 2, 2016). "Subways we already have are doomed by built-in flaws: James". Toronto Star. Archived from the original on March 3, 2016. Retrieved March 2, 2016.
  75. ^ "Transportation Master Plan". York Region. October 5, 2021. Archived from the original on October 17, 2022. Retrieved October 17, 2022.
  76. ^ "Future Projects Map". vivaNext. Archived from the original on April 22, 2023. Retrieved April 22, 2023.