The Kanakadurga Flyover (also known as Durga Temple Flyover) is a flyover spanning the Krishna River and Prakasam Barrage in Vijayawada, India. As of 2022, it is the longest flyover in Andhra Pradesh with a length of 2.6 kilometres (1.6 mi). It was opened on 16 October 2020 by Nitin Gadkari.[1]

Kanakadurga Flyover

కనకదుర్గ వారధి
Coordinates16°30′46″N 80°36′14″E / 16.51278°N 80.60389°E / 16.51278; 80.60389
Carries6 lanes of road
CrossesKrishna River, Prakasam Barrage
LocaleVijayawada
Other name(s)Durga Temple Flyover
Characteristics
DesignBeam bridge
Total length2.6 kilometres (1.6 mi)
Width23.7 metres (78 ft)
No. of spans47
History
Construction start22 November 2015
Construction end30 August 2020
Construction cost₹458 Crores
Opened30 September 2020 (2020-09-30)
Location
Map

Geography

edit

The Kanakadurga Flyover is built around Indrakeeladri Hill on which Kanaka Durga Temple is located.[citation needed] It spans from Bhavanipuram near Gollapudi to PNBS. Road widening works have been completed up to Kanaka Durga Varadhi. This project has a total length of 5.29 kilometres (3.29 mi), of which 2.3 kilometres (1.4 mi) are flyover and the remaining 2.9 kilometres (1.8 mi) are road widening works. This flyover crosses Krishna River, Prakasam Barrage[2] and Buckingham Canal near Indrakeeladri hill,[3] and meets NH65[4] near PNBS.[5]

History

edit

After bifurcation, a flyover was proposed by the government of Andhra Pradesh to control traffic flow between the new state capital Amaravati and the de facto capital Hyderabad on the existing 15-20 foot highway around Durga temple.[6] The construction of the Kanakadurga Flyover was started by Soma Company of Hyderabad on 22 November 2015 and the road level bridge was completed by 2016 for Krishna Pushkaralu. The flyover was very difficult to construct due to its plan and on the River Krishna.[clarification needed] The land acquisition for this project cost around 100 crores for the shifting of utilities like drinking water pipelines along the road. The construction deadline was extended repeatedly between 2017 and 2020, and construction was finally completed by 30 August 2020.[7]

Construction

edit

It is a six-lane highway with a width of 23.7 metres.[8] It is the third of its kind in India to use pre-stress technology. It is estimated to have cost 282.4 crores, which was later adjusted to 440 crores for inflation.[9] It has a unique and complex design with a six-lane corridor supported by a single pillar.[9] There are two underpasses in the flyover master plan. Vertical gardening has been done on the column of this flyover along with a park for F1H2o to celebrate the 2018 F1H2o World Championship in Amaravati.[10] The district administration has decided to allow traffic through the flyover prior to its completion to prevent traffic bottlenecks and congestion.[6]

See also

edit

References

edit
  1. ^ "At last, Kanaka Durga flyover opened in Vijayawada". The New Indian Express. Retrieved 18 October 2020.
  2. ^ Staff Reporter (19 November 2018). "Gateway project at riverfront set in motion". The Hindu. ISSN 0971-751X. Retrieved 24 November 2018.
  3. ^ "Private firm to maintain sanitation at Durga Ghat". The New Indian Express. 12 November 2018. Retrieved 22 May 2019.
  4. ^ "Andhra Pradesh moving towards no-potholes roads - Times of India". The Times of India. Retrieved 24 November 2018.
  5. ^ "Vijayawada: Alternative route for heavy vehicles to reduce city traffic". The New Indian Express. Retrieved 24 November 2018.
  6. ^ a b "Motorists in for a dangerous ride on Durga flyover - Times of India". The Times of India. Retrieved 24 November 2018.
  7. ^ "Durga temple flyover not before 2019: Govt". The Hans India. Retrieved 24 November 2018.
  8. ^ "Kanakadurga flyover works drag on". Deccan Chronicle. 27 October 2018. Retrieved 24 November 2018.
  9. ^ a b "Amazing Pics Of Kanaka Durga flyover". Gulte.com. Retrieved 24 November 2018.
  10. ^ "First vertical organic garden coming up in Vijayawada". The New Indian Express. Retrieved 24 November 2018.