West of Duddon Sands Wind Farm

West of Duddon Sands Wind Farm (WoDS), occasionally also known as West Duddon Wind Farm is an offshore wind farm located 14 kilometres (8.7 mi) south west of Walney Island off the coast of Barrow-in-Furness[1] in Cumbria, in the Irish Sea, England. It was developed by Scottish Power and Ørsted A/S.

West of Duddon Sands Wind Farm
West of Duddon Sands Wind Farm viewed from Blackpool
Map
Country
  • United Kingdom
Location10 Miles south west of Walney Island Cumbria
Coordinates53°59′N 3°28′W / 53.98°N 3.46°W / 53.98; -3.46
StatusOperational
Construction beganMay 2013
Commission date
  • October 2014
Construction cost
  • £1,600 million
Wind farm
Type
Distance from shore14 km (8.7 mi)
Rotor diameter
  • 120 m (390 ft)
Site area67 km2 (26 sq mi)
Power generation
Units operational108 × 3.6 MW
Make and modelSiemens Gamesa SWT-3.6-120 (108)
Nameplate capacity
  • 389 MW
External links
Websitewestofduddonsands.co.uk
CommonsRelated media on Commons
Map
Wind farm layout

Location

edit

The wind farm gets its name from a large sand bank uncovered at low water in the mouth of the estuary of the River Duddon to the north of the Furness Peninsula. The farm actually lies to the south west of the Duddon Sands and covers an area of approximately 67 km2.

It is situated in the vicinity of three other wind farms. It is to the south of the Walney Wind Farm and Ormonde Wind Farm, and to the west of the Barrow Offshore Wind Farm.[2]

Ownership

edit

The project to develop the West of Duddon Sands Wind Farm was awarded in December 2003 as part of the Round 2 development programme.[3] The project was awarded to Morecambe Wind Ltd, a partnership between Scottish Power, Elsam, and Eurus Energy.[3] Elsam, a Danish company, was later acquired by DONG Energy. By 2014 the windfarm was stated to be "a joint venture project between ScottishPower Renewables and Dong Energy".[4]

Planning

edit

The project included constructing the wind turbines and their foundations, building offshore substations, installing power cables both undersea and onshore, as well as an extension to the existing onshore Electrical substation to house the equipment needed for connection into the UK National Grid. Cables were supplied by NKT, and are 82 km of 155 kV sea cables and 22 km land cables, at a price of DKK 600 million.[5]

The wind farm planning application was filed in April 2006 and consent was granted in September 2008.[6] The application was for between 83 and 139 turbines with a nameplate capacity of 500 MW.[7] However permission was granted for only 108 turbines due to geological siting issues. This will provide up to 389 MW of power.

Construction

edit

The 108 Siemens Wind Power 3.6 MW geared turbines cost €700 million installed, bringing the cost per turbine to €6.5m, or €1.8m per MW. Adding maintenance, transformator platform and cabling to shore brings the cost to £1.6 billion.[8][9] A cable was laid by Stemat Spirit, shown in TV documentary Mighty Ships.[10] The project has a 5-year warranty. Electrical work started in 2012, turbines installed in 2013, and operating in 2014.[11]

The wind farm began generating power on 28 January 2014 when four turbines were connected to the grid.[12] The final turbine was installed in June 2014.[13] The wind farm was officially inaugurated by the Secretary of State for Energy and Climate Change, Ed Davey on 30 October 2014.[14]

References

edit
  1. ^ Iberdrola, Dong Energy order Siemens turbines for West of Duddon Sands offshore wind farm RenewBL, 27 June 2011. Accessed: 22 March 2012.
  2. ^ "West of Duddon Sands Offshore Wind Farm". Dong energy. Retrieved 30 January 2014.
  3. ^ a b "History". www.westofduddonsands.co.uk. Retrieved 21 January 2015.
  4. ^ "West of Duddon Sands". www.scottishpowerrenewables.com. Retrieved 21 January 2015.
  5. ^ NKT wind sea cable order for Scottish wind farm Metal Industry, 1 August 2011. Accessed: 11 December 2011.
  6. ^ 4C Offshore database for West of Duddon Sands
  7. ^ "UKWED Offshore wind farms". RenewableUK. Archived from the original on 19 March 2011. Retrieved 24 February 2011.
  8. ^ The cost of an offshore wind turbine Hub North, 4 July 2011. Accessed: 22 March 2012. Quote: "This makes the price of one of Siemens turbines approx. 6.5 million euros, corresponding to 48.5 million kr or 13.4 million kr per MW"
  9. ^ Iberdrola Orders $993 Million of Siemens Turbines for Wind Farm Bloomberg, 27 June 2011. Accessed: 22 March 2012.
  10. ^ "Mighty Ships Episodes". Discovery.ca. Bell Media Television. Retrieved 1 July 2014.
  11. ^ Stubben, Charlotte. Iberdrola reveals how much Siemens receives on major turbine deal Metal Supply, 28 June 2011. Accessed: 22 March 2012.
  12. ^ "Huge new windfarm generating power off Cumbrian coast". North-West Evening Mail. 28 January 2014. Retrieved 28 January 2014.
  13. ^ "West of Duddon Sands wind farm final turbine installed". BBC News. 28 January 2014. Retrieved 18 June 2014.
  14. ^ "Edward Davey opens West of Duddon Sands Offshore Wind Farm". www.gov.uk. 30 October 2014. Retrieved 12 December 2015.
edit