Expressways are the highest class of roads in India. As of December 2024, the total length of expressways in India was 6,059 km (3,765 mi), with 11,127.69 km (6,914.43 mi) under construction. As per NHAI and Indian Roads Congress, expressways are access controlled highways with a divided carriageway, designed for high speed vehicular movement and heavy traffic.[1] There is a central reservation or median that separates the flow travelling in opposite directions. Entrance and exits are provided only by grade separated interchanges. The interchanges may be system interchanges (such as cloverleaf, three-way, trumpet) used with other national or state highways or be service interchanges (such as SPDI) used with smaller roads.[2] In contrast, National highways may or may not be divided by a median and may or may not have access control.[3] Some highways, built by State Governments, which may be fully access controlled or may be limited access controlled, are declared or named as expressways by their respective State Governments.[4]
Expressways of India | |
---|---|
System information | |
Maintained by Ministry of Road Transport and Highways | |
Length | 6,059 km (3,765 mi) |
Formed | 2002 |
Highway names | |
System links | |
As of 2024, the longest expressway in India is the partially-opened Delhi–Mumbai Expressway (Phase-III) at 935 km (581 mi), which was opened in 2023,[5] and the widest expressway is the Delhi – Gurgaon section of the Dwarka Expressway with 16 lanes, which was opened in 2024.
Development and timeline
editGreenfield Expressways in India are designed as 12-lane wide Expressways with the initial construction of 8 lanes with maximum speed set as 120 km/h for all type of vehicles. Land for 4-lane future expansion is reserved in the center of the expressways. Greenfield Expressways are designed to avoid inhabited areas and go through new alignments to bring development to new areas and to reduce land acquisition costs and construction timelines. The Delhi–Mumbai Expressway is an example of a new 12-lane approach with initial 8-lane construction.
Bharatmala is an ecosystem of road development which includes tunnels, bridges, elevated corridors, flyovers, overpass, interchanges, bypasses, ring roads etc. to provide shortest & optimized connectivity to multiple places, it is a centrally-sponsored and funded road and highways project of the Government of India[6] with a target of constructing 83,677 km[7] of new highways over the next five years, was started in 2017 as well as conversion of 4 lane highways into 6 lane Brownfield expressways & some state highways into NH/NE.[8] Phase I of the Bharatmala project involves the construction of 34,800 km of highways (including the remaining projects under NHDP) at an estimated cost of ₹5.35 lakh crore by 2021–22.[9]
Brownfield National Highway Project is the widening/re-development of existing National Highways. The upgradation of highway is a Brownfield Expressway Project which has high traffic demand and is a part of both rural and urban setup. The upgradation is carried from 4 Lane to 6 Lane on EPC mode such as NH-709A.[10] 43,000 km state highways have been converted to National Highways in last 8 years.[11]
The majority of the investment required for constructing expressways comes from the central government. Uttar Pradesh and Maharashtra are the only states which are investing in building expressways through dedicated expressway corporations.[12]
The National Highways Authority of India operating under the Ministry of Road Transport and Highways will be in-charge of the construction and maintenance of expressways.[13] The National Highways Development Project by the government of India aims to expand the country's current expressway network and plans to add an additional 18,637 km of greenfield expressways by 2025 apart from building 4 lane greenfield national highways of 50,000 km length.[14][15] Currently NHDP Phase-6 and NHDP Phase-7 construction is going on along with Bharatmala project.
The Ministry of Road Transport and Highways is set to unveil a plan for constructing 50,000 km of new expressways by 2037 in the first 100 days of the new government.The program, replacing Bharatmala, aligns with Vision 2047 and aims to reduce logistic costs and modernize road infrastructure.[16]
Economic Corridors/Industrial Corridors
editEconomic Corridors of India or Industrial Corridors of India, 44 corridors 26,200 km (16,300 mi) were identified and 9,000 km (5,600 mi) will be taken up in phase-I, they exclude 6 National Corridors, they include:[17] 66 8,000 km (5,000 mi) inter-corridors (IC) & 116 7,500 km (4,700 mi) feeder routes (FR) were identified for Bharatmala.[17]
List of 44 economic corridors (EC):[17]
- EC-1: Mumbai-Kolkata
- EC-2: Mumbai-Kanyakumari
- EC-3: Amritsar-Jamnagar
- EC-4: Kandla-Sagar
- EC-5: Agra-Mumbai
- EC-6: Pune-Vijayawada
- EC-7: Raipur-Dhanbad
- EC-8: Ludhiana-Ajmer
- EC-9: Surat-Nagpur
- EC-10: Hyderabad-Panaji
- EC-11: Jaipur-Indore
- EC-12: Solapur-Nagpur
- EC-13: Sagar-Varanasi
- EC-14: Kharagpur-Siliguri
- EC-15: Raipur-Visakhapatnam
- EC-16: Delhi-Lucknow
- EC-17: Chennai-Kurnool
- EC-18: Indore-Nagpur
- EC-19: Chennai-Madurai
- EC-20: Mangaluru-Raichur
- EC-21: Tuticorin-Cochin
- EC-22: Solapur-Bellary-Gooty
- EC-23: Hyderabad-Aurangabad
- EC-24: Delhi-Kanpur
- EC-25: Tharad-Phalodi
- EC-26: Nagaur-Mandi Dabwali
- EC-27: Sagar-Lucknow
- EC-28: Sambalpur-Paradeep
- EC-29: Amreli-Vadodra
- EC-30: Godhra-Khargone
- EC-31: Sambalpur-Ranchi
- EC-32: Bengaluru-Malappuram
- EC-33: Raisen-Pathariya
- EC-34: Bengaluru-Mangaluru
- EC-35: Chittaurgarh-Indore
- EC-36: Bilaspur-New Delhi
- EC-37: Solapur-Mahabubnagar
- EC-38: Bengaluru-Nellore
- EC-39: Ajmer-Udaipur
- EC-40: Sirsa-Delhi
- EC-41: Sirohi-Beawar
- EC-42: Jaipur-Agra
- EC-43: Pune-Aurangabad
- EC-44: North East Corridor
Timeline of total length of Expressways
editYear | Total Length in (KM) |
---|---|
2024–2025 (Preliminary) | |
2023–2024 | |
2022–2023 | |
2021–2022 | |
2020–2021 | |
2019–2020 | |
2018–2019 | |
2017–2018 | |
2016–2017 | |
2015–2016 | |
2014–2015 | |
2013–2014 | |
2012–2013 | |
2011–2012 | |
2010–2011 | |
2009–2010 | |
2008–2009 | |
2007–2008 | |
2006–2007 | |
2005–2006 | |
2004–2005 | |
2003–2004 | |
2002–2003 | |
2001–2002 |
State-wise overview of expressways
editList of operational expressways by state, as of March 2023:
States | Length (km/mi) | Number of Expressways (by NHAI) |
---|---|---|
Uttar Pradesh (list) | 1,500 km (930 mi) | 8 |
Maharashtra (list) | 828.9 km (515.1 mi) | 6 |
West Bengal (list) | 189 km (117 mi) | 3 |
Haryana (list) | 627 km (390 mi) | 7 |
Madhya Pradesh (list) | 271 km (168 mi) | 4 |
Gujarat | 262.4 km (163.0 mi) | 2 |
Rajasthan (list) | 840 km (520 mi) | 3 |
Punjab (list) | ||
Karnataka | 251 km (156 mi) | 5 |
Chhattisgarh (list) | 191 km (119 mi) | 3 |
Telangana | 169.6 km (105.4 mi) | 2 |
Tamil Nadu | 94.8 km (58.9 mi) | 2 |
Jharkhand (list) | 86 km (53 mi) | 1 |
Bihar (list) | 33 km (21 mi) | 2 |
Uttarakhand | 30.17 km (18.75 mi) | 2 |
Expressways by NHAI
editThis list contains expressways built by National Highways Authority of India (NHAI) and declared or named as expressways by Government of India. These Expressways are run through one or more states or UTs; some of these are designated with "NE" tag while some are not but both of the types are National Expressways.[18]
Fully operational Under construction Partially operational and partially under construction Planned but construction not started |
Expressways designated with "NE"
editName | Designation | State(s) and UT(s) | Lanes | Total Length (km) | Date declared as NE | Operational since |
---|---|---|---|---|---|---|
Ahmedabad–Vadodara Expressway | NE 1 | Gujarat | 4 | 93 | 13 March 1986[19] | 16 August 2004[20] |
Eastern Peripheral Expressway | NE 2 | Haryana, Uttar Pradesh | 6 | 135 | 30 March 2006[21] | 27 May 2018[22] |
Delhi–Meerut Expressway | NE 3 | Delhi, Uttar Pradesh | 14 | 96 | 18 Jun 2020[23] | 1 April 2021[24] |
Delhi–Mumbai Expressway | NE 4 | Haryana, Rajasthan, Madhya Pradesh, Gujarat and Maharashtra | 8 | 1380 | 10 Jan 2020[25] | Partially operational (as of 2024) since March 2023 |
Delhi–Amritsar–Katra Expressway | NE 5 | Delhi, Jammu and Kashmir, Haryana, Punjab | 4 | 398 | 25 Jun 2020[26] | Expected: January 2025 |
Awadh Expressway | NE 6 | Uttar Pradesh | 6 | 62 | 15 Dec 2020[27] | Expected: December 2024 |
Bangalore–Chennai Expressway | NE 7 | Karnataka, Tamilnadu | 4 | 258 | 1 Jan 2021[28] | Karnataka section is operational, rest is under construction. |
Varanasi–Kolkata Expressway | NE 8 | Uttar Pradesh, Bihar, Jharkhand, West Bengal | 6 | 652 | 1 Jan 2023 | Expected: December 2026 |
Kharagpur–Morgram Expressway | NE 9 | West Bengal | 4 | 230 | 1 Jan 2023 | Expected: December 2026 |
Katihar-Kishanganj-Siliguri-Guwahati Expressway | NE 10 | Bihar, West Bengal, Assam | 676 | 1 Jan 2023 | Expected: December 2026 |
Spur Expressways are branch expressways from other expressways.
Spur from | Name | Designation | State(s)/ UT(s) | Length (km/mi) | Lanes | Operational since | Remarks |
---|---|---|---|---|---|---|---|
NE4 | Jaipur-Bandikui Expressway[29] | NE4C | Rajasthan | 4 | 2025–12 |
| |
NE5 | Nakodar–Amritsar Expressway | NE 5A | Punjab | 99 | 4 | Expected: January 2025 |
Economic corridor expressways
editThese expressways (all built by NHAI) are part of Economic corridors (EC) and have been declared or named as Expressway by Government of India.
Name | Part of | State(s)/ UT(s) | Length (km/mi) | Lanes | Operational since | Remarks |
---|---|---|---|---|---|---|
Amritsar–Jamnagar Expressway[30] | EC-03 | Punjab, Haryana, Rajasthan, Gujarat | 1257 km 310.7 mi |
4 | July 2023 | 2nd Longest Expressway in India. |
Raipur-Ranchi-Dhanbad Expressway | EC-07 | Chhattisgarh, Jharkhand | 465 km (288.9 mi) | 4 | Expected: 2026 | |
Ludhiana–Bathinda–Ajmer Expressway[31] | EC-08 | Punjab, Rajasthan, Haryana | 75.5 km (46.9 mi) | 6 | Expected: 2025-08 | |
Kharagpur Moregram Expressway | EC-14 | West Bengal | 230 km (140 mi) | 4 | Expected: 2026 | |
Raipur–Visakhapatnam Expressway[32] | EC-15 | Chhattisgarh, Odisha, Andhra Pradesh | 465 km (288.9 mi) | 4 | Expected: 2025–03 |
Other inter-state expressways
editThe following list refers to the expressways which passing through more than one state/UT and connect places from different states/UTs. Bypass or spur expressways are not included in following list.
Name | State(s)/ UT(s) | Length (km/mi) | Lanes | Operational since | Remarks |
---|---|---|---|---|---|
Delhi–Noida Direct Flyway (DND)[33] | Delhi, Uttar Pradesh | 9.2 km 5.7 mi |
8 | January 2001 | India's first 8-laned expressway. |
Delhi–Gurgaon Expressway[34] | Delhi, Haryana | 27.7 km 17.2 mi |
6-10 | January 2008 | Part of the Golden Quadrilateral. |
Delhi–Panipat Expressway[35] | Delhi, Haryana | 70.5 km 43.8 mi |
8 | June 2023 | |
Delhi–Faridabad Skyway[36][37] | Delhi, Haryana | 4.4 km 2.7 mi |
6 | November 2010 | Part of NH44. |
Delhi–Dehradun Expressway[38] | Delhi, Uttar Pradesh, Uttarakhand | 210 km (130 mi) | 6 | December 2024 | |
DND–KMP Expressway | Delhi,Harayana | 60 km 37.3 mi |
6 | November 2024 | 50 km completed in November 2024, rest 9 km is remaining |
Kharagpur Visakhapatnam Expressway | West Bengal, Orissa, Andhra Pradesh | 783 km 486.5 mi |
6 | ||
Bangalore–Vijayawada Expressway[39] | Karnataka, Andhra Pradesh | 624 km (387.7 mi) | 6 | Expected: 2026 | |
Surat–Chennai Expressway[10][40] | Gujarat, Maharashtra, Karnataka, Telangana, Andhra Pradesh, Tamil Nadu | 1,271 km (789.8 mi) | 4 | Expected: December 2026 | |
Atal Progress-Way (Chambal Expressway)[41] | Rajasthan, Madhya Pradesh, Uttar Pradesh | 404 km (251 mi) | 6 | Expected: 2027 | |
Ambala-Shamli Expressway | Haryana, Uttar Pradesh | 120 km (75 mi) [42] | 6 | Expected: 2025 | |
Faridabad–Noida–Ghaziabad Expressway | Delhi, Haryana, Uttar Pradesh | 56 km (35 mi) | 6 | ||
Delhi–Jaipur Super Expressway | Rajasthan, Haryana | 195 km (121.2 mi) | Expected: 2027–01 | ||
Indore-Hyderabad Expressway | Madhya Pradesh, Telangana | 713 km (443 mi) | Expected: 2025–12 | ||
Khammam–Devarapalli Expressway | Telangana, Andhra Pradesh | 162 km (101 mi) | 4 |
| |
Urban Extension Road-II | Delhi | 75.7 km (47.0 mi) | 6 | Expected: 2024–12 | |
Nagpur–Vijayawada Expressway[43][44] | Maharashtra, Telangana, Andhra Pradesh | 457 km (284 mi) | 2026 |
State expressways by NHAI
editThe following list refers to the expressways built by NHAI to connect areas within the state. Bypass or spur expressways are not included in following list.
Name | States | Start | End | Length (km/mi) | Lanes | Operational since | Remarks |
---|---|---|---|---|---|---|---|
Trans-Haryana Expressway[45] | Haryana | Kurukshetra | Mahendragarh | 227 km 141.1 mi |
6 | August 2022 | Greenfield expressway created as NH 152D |
Durgapur Expressway | West Bengal | Kolkata | Durgapur | 158 km 98.2 mi |
6 | ||
Raipur–Bilaspur Expressway | Chhattisgarh | Raipur | Bilaspur | 127 km 78.9 mi |
4-6 | May 2019 | Connects Judicial Capital Bilaspur and State Capital Raipur |
Jaipur–Kishangarh Expressway[46] | Rajasthan | Jaipur | Kishangarh | 90 km 55.9 mi |
6 | April 2005 | Forms a segment of the NH-8. |
Kona Expressway Elevated Corridor | West Bengal | Nibra | Shibpur | 14.17 km 8.8 mi |
6 | 2029 | |
Amas–Darbhanga Expressway[47] | Bihar | Amas | Darbhanga | 189 km (117.4 mi) | 4 | 2027-12 | Bihar's first expressway by NHAI |
Wazirabad–Mayur Vihar Elevated Expressway | Delhi NCR | 18 km (11 mi) | 6 | Expected 2027 | |||
Paniyala–Barodameo Expressway | Rajasthan | Paniyala | Barodameo | 86.5 km (53.7 mi) | 6 | 2025–12 | |
Panipat–Dabwali Expressway[48] | Haryana | Panipat | Dabwali | 300 km (190 mi) | 4 | 2026–12 | |
Ranchi–Jamshedpur Expressway[49][50][51] | Jharkhand | Ranchi | Jamshedpur | 220 km (140 mi) | 4 | 2026–12 | |
Ahmedabad–Dholera Expressway[52] | Gujarat | Ahmedabad | Dholera | 110 km (68 mi) | 2025–03 | ||
Bhopal-Indore Expressway[53] | Madhya Pradesh | Bhopal | Indore | 157 km (97.6 mi) | 6 | 2026 | |
Chennai Port–Maduravoyal Expressway[54][55] | Tamil Nadu | Chennai Port | Maduravoyal | 20.6 km (12.8 mi) | 6 | Expected: 2025–12 | |
Ghazipur–Ballia–Manjhighat Expressway[56] | Uttar Pradesh | Ghazipur | Manjhighat | 132.76 km (82.5 mi) | Expected: 2025-03[57] |
| |
Jind-Gohana Expressway[58] | Haryana | Jind | Sonipat | 40.6 km (25.2 mi) | 6 | Expected: 2025–03 | |
Mumbai–Pune Missing Link Expressway | Maharashtra | Mumbai | Pune | 13.3 km (8.3 mi) | 6 | Expected: 2025-08[59] |
Bypass expressways
editBypass Expressways such as ring roads, bypass roads, freeways and elevated roads are used to bypass city core traffic. These are declared as expressways by Government of India. These direct heavy traffic to the outskirts freeing city roads of traffic. This also allows outside traffic to directly pass the city instead of going through it further limiting traffic within a city.
Name | Bypassing city | State(s)/ UT(s) | Length (km/mi) | Lanes | Operational since | Remarks |
---|---|---|---|---|---|---|
Eastern Peripheral Expressway | New Delhi | Uttar Pradesh, Haryana | 135 km 83.9 mi |
6 | May 2018 | Part of ring road for Delhi NCR. |
Western Peripheral Expressway | New Delhi | Haryana | 135.6 km 84.3 mi |
6 | November 2018 | Part of ring road for Delhi NCR. |
Ranchi Ring Road | Ranchi | Jharkhand | 86 km 53.4 mi |
6 | February 2019 | First Expressway of Jharkhand by NHAI. |
Prayagraj Bypass Expressway | Prayagraj (Allahabad) | Uttar Pradesh | 84.7 km 52.6 mi |
4 | April 2009 | First Expressway of Uttar Pradesh. |
Chennai Bypass[60] | Chennai | Tamil Nadu | 32 km 19.9 mi |
4-6 | June 2010 | First Expressway of Tamil Nadu. |
Mumbai Trans Harbour Link | Mumbai, Navi Mumbai | Maharashtra | 21.8 km 13.5 mi |
6 | January 2024 | |
Belghoria Expressway | Kolkata | West Bengal | 16 km 9.9 mi |
4 | 2008 | |
Chatrapati Shivaji Maharaj Uddanpul (Nashik Freeway) | Nashik | Maharashtra | 16 km 9.9 mi |
4-6 | June 2013 | First expressway in Maharashtra by NHAI |
Panipat Elevated Expressway[61] | Panipat | Haryana | 10 km 6.2 mi |
6 | January 2008 | |
Dwarka Expressway | Gurgaon | Delhi, Haryana | 18 km 11.2 mi |
16 | Mar 2024 | Partially opened, with remaining portion expected to be completed in 2024 |
Lucknow Outer Ring Road | Lucknow | Uttar Pradesh | 104 km 64.6 mi |
6 | Mar 2024 | |
Satellite Town Ring Road | Bangalore | Karnataka | 80 km 49.7 mi |
8 | Mar 2024 | Partially operational |
Ludhiana Elevated Corridor | Ludhiana | Punjab | 13 km 8.1 mi |
6 | Feb 2024[62] |
|
Varanasi Ring Road[63][64] | Varanasi | Uttar Pradesh | 63 km (39 mi) | Expected: 2025-03 |
Expressways declared by state
editThese expressways are built by State Governments in their respective states and declared as expressways by that State Government, not by Government of India. Most of these highways contain characteristics of expressways.
Fully operational Under construction Partially operational and partially under construction Planned but construction not started |
State | Name | Length (km/mi) | Lanes | Status
|
---|---|---|---|---|
Telengana | Outer Ring Road, Hyderabad[65] | 158 km 98.2 mi |
8 | Fully operational since April 2018
|
P. V. Narasimha Rao Expressway[66][67] | 11.6 km 7.2 mi |
4 | Fully operational since October 2009
| |
Maharashtra | Mumbai–Nagpur Expressway | 625 km 388.4 mi |
6 | Expected full operational from January 2025[68] |
Coastal Road | 29.2 km 18.1 mi |
8 | Phase 1 is operational and phase 2 is under construction | |
Mumbai–Pune Expressway | 94.5 km 58.7 mi |
6 | Fully operational since April 2002 | |
Eastern Freeway | 16.8 km 10.4 mi |
4 | Fully operational since June 2014 | |
Airoli–Katai Naka Freeway | 12.3 km (7.6 mi) | 6 | Expected completion: 2025 | |
Versova–Bandra Sea Link | 19.22 km (11.9 mi) | 8 | Expected completion: 2026–12 | |
Jharkhand | Dhanbad-Bokaro-Ranchi-Jamshedpur Industrial Expressway[69][51] | 400 km (248.5 mi) | 4 | Fully operational since August 2023 |
Uttar Pradesh | Bundelkhand Expressway | 296 km 183.9 mi |
4 | Fully operational since July 2022 |
Purvanchal Expressway[70] | 296 km 183.9 mi |
4 | Fully operational since November 2021 | |
Agra–Lucknow Expressway[71] | 302.2 km 187.8 mi |
6 | Fully operational since February 2017 | |
Yamuna Expressway[72][73] | 165.5 km 102.8 mi |
6 | Fully operational since August 2012 | |
Noida–Greater Noida Expressway[74] | 24.5 km 15.2 mi |
6 | Fully operational since 2002 | |
Kanpur Ring Road | 93 km 57.8 mi |
6 | Expected to be completed in 2027 | |
Ganga Expressway[75] | 594 km (369.1 mi) | 6 | Expected to be completed in 2024 | |
Gorakhpur Link Expressway[76] | 91.40 km (56.8 mi) | 4 | Expected completion: 2024
| |
West Bengal | Kalyani Expressway | 24.5 km 15.2 mi |
4–6 | Partially operational (as of 2024)
|
Chhattisgarh | Raipur–Naya Raipur Expressway | 12 km 7.5 mi |
4 | Fully operational since 2019 |
Bihar | Loknayak Ganga Path Phase I | 20.5 km 12.7 mi |
4 | Fully operational since June 2022 |
Loknayak Ganga Path | 18 km (11 mi) | 4 |
| |
Gujarat | Surat Outer Ring Road | 66 km (41.0 mi) | Expected completion: 2026–12 | |
Madhya Pradesh | Garoth-Ujjain Expressway[77] | 136 km (85 mi) | Expected completion: 2025–06 |
Planned expressways
editName | States | Length (km/mi) |
---|---|---|
Farrukhabad Link Expressway[78] | Uttar Pradesh | 98 km (60.9 mi) |
Sambalpur-Ranchi Expressway[79] | Orissa, Jharkhand | 147 km (91.3 mi) |
Wazirabad-IGI Airport Elevated Expressway[80] | New Delhi | 29 km (18.0 mi) |
Kharagpur–Burdwan–Moregram Expressway | West Bengal | 230 km (142.9 mi) |
Sewri-Worli Elevated Corridor[81] | Mumbai | 4.51 km (2.8 mi) |
Shamli-Bareilly Expressway[82] | Uttar Pradesh | 220 km (136.7 mi) |
Agra–Gwalior Expressway[83] | Uttar Pradesh, Madhya Pradesh | 88.4 km (54.9 mi) |
Aurangabad–Darbhanga Expressway[84] | Bihar | 271 km (168.4 mi) |
Ballia Link Expressway[85] | Uttar Pradesh | 30 km (19 mi) |
Bangalore-Mangalore Expressway[86] | Karnataka | 360 km (220 mi) |
Bangalore Peripheral Ring Road | Karnataka | 74 km (46 mi) |
Bhandara–Gadchiroli Expressway[87] | Maharashtra | 156 km (97 mi) |
Chirle-Palaspe Elevated Corridor[88] | Navi Mumbai | 6.5 km (4.0 mi) |
Pune–Bengaluru Expressway | Karnataka, Maharashtra | 700 km (430 mi) |
Patna–Purnia Expressway[89] | Bihar | 308 km (191.4 mi) |
Delhi–Hisar–Fazilka Expressway[90] | Haryana | 170 km (105.6 mi) |
Virar–Alibag Expressway[91] | Maharashtra | 126 km (78.3 mi) |
Ghaziabad–Kanpur Expressway[92] | Uttar Pradesh | 380 km (236.1 mi) |
Ganga Expressway Phase-2[93][94][95][96] | Uttar Pradesh, Uttarakhand | 424 km (263.5 mi) |
GMADA Expressway | Chandigarh, Haryana, Punjab | 284 km (176 mi) |
Gorakhpur-Shamli Expressway | Haryana, Uttar Pradesh | 700 km (430 mi) |
Pune–Nashik Industrial Expressway[97][98] | Maharashtra | 250 km (160 mi) |
Pune–Aurangabad Expressway[99] | Maharashtra | 225 km (140 mi) |
Gorakhpur–Siliguri Expressway[89][100] | Uttar Pradesh, Bihar, West Bengal | 607 km (377.2 mi) |
Raipur–Hyderabad Expressway[101] | Chhattisgarh, Maharashtra, Telangana | 530 km (330 mi) |
High Capacity Mass Transit Route(HCMTR)[102] | Pune | 35.96 km (22.34 mi) |
Honnavar-Bangalore[86] | Karnataka | 325 km (202 mi) |
Indore–Kota Expressway[103] | Rajasthan, Madhya Pradesh | 136 km (85 mi) |
Jalna-Nanded Expressway[103] | Maharashtra | 179 km (111 mi) |
Konkan Greenfield Expressway | Maharashtra | 500 km (310 mi) |
Khargar Coastal Road[104] | Maharashtra | 9.6 km (6.0 mi) |
Mangalore-Panaji Expressway[86] | Karnataka | 400 km (250 mi) |
Mysuru–Kushalnagar Expressway[105] | Karnataka | 115 km (71 mi) |
Nagpur-Bhandara-Gondia Expressway[106] | Maharashtra | 127 km (79 mi) |
Nagpur–Chandrapur Expressway[107] | Maharashtra | 221 km (137 mi) |
Nagpur–Hyderabad–Bengaluru Expressway[108] | Maharashtra, Telangana, Andhra Pradesh, Karnataka | 1,100 km (680 mi) |
Nagpur–Goa Expressway[109][110] | Maharashtra | 802 km (498 mi) |
Prayagraj Link Expressway[111] | Uttar Pradesh | 193 km (120 mi) |
Pune Ring Road | Maharashtra | 128 km (80 mi) |
Meerut–Haridwar Expressway[112] | Uttar Pradesh, Uttarakhand | 120 km (75 mi) |
Rampur–Rudrapur Expressway[112] | Uttar Pradesh, Uttarakhand | 50 km (31 mi) |
Regional Ring Road, Hyderabad | Telangana | 330 km (210 mi) |
Chitrakoot–Prayagraj Expressway[112] | Uttar Pradesh | 130 km (81 mi) |
Tharad-Ahmedabad Expressway[113] | Gujarat | 213 km (132 mi) |
Ulwe Coastal Road[104] | Maharashtra | 7 km (4.3 mi) |
Versova-Dahisar Coastal Road[114] | Maharashtra | 22.6 km (14.0 mi) |
Vindhya Expressway[112] | Uttar Pradesh | 190 km (120 mi) |
Vindhya Expressway[115] | Madhya Pradesh | 660 km (410 mi) |
Narmada Expressway[116][117] | Madhya Pradesh | 1,300 km (810 mi) |
Outer Ring Road, Amaravati[118] | Andhra Pradesh | 220 km (136.7 mi) |
Outer Ring Road, Patna | Bihar | 140 km (87 mi) |
Palakkad–Kozhikode Greenfield Highway | Kerala | 121 km (75 mi) |
Thiruvananthapuram–Angamaly Greenfield Highway | Kerala | 257 km (160 mi) |
Durg–Raipur–Arang Expressway | Chhattisgarh | 92 km (57 mi) |
Haldia–Raxaul Expressway | Bihar, Jharkhand, West Bengal | 650 km (400 mi) |
Outer Ring Road, Thiruvananthapuram[119] | Kerala | 80 km (50 mi) |
Varanasi Link Expressway[120][121] | Uttar Pradesh | 13 km (8.1 mi) |
Total | 16,050.7 km (8,815 mi) |
Proposed expressways
editName | States | Length (km/mi) |
---|---|---|
Bareilly–Gorakhpur Expressway[125] | Uttar Pradesh | 500 km (310 mi) |
Chennai–Salem Expressway[126] | Tamil Nadu | 277 km (172 mi) |
Chennai–Trichy–Thanjavur Expressway | Tamil Nadu | 310 km (190 mi) |
Delhi–Hisar Expressway | Haryana | 170 km (110 mi) |
Durg–Raipur–Arang Expressway | Chhattisgarh | 92 km (57 mi) |
Gurugram–Faridabad Expressway | Haryana | 135 km (84 mi) |
Indore–Mumbai Expressway | Madhya Pradesh, Maharashtra | 515 km (320 mi) |
Gorakhpur–Shamli Expressway[127][128][129] | Uttar Pradesh | 840 km (520 mi) |
Kharagpur–Kolkata Expressway | West Bengal | 120 km (75 mi) |
Kharagpur–Siliguri Expressway | West Bengal | 516 km (321 mi) |
Mangaluru–Chitradurga Expressway | Karnataka | 196 km (122 mi) |
Pathankot–Ajmer Expressway[130] | Rajasthan, Haryana, Punjab | 600 km (370 mi) |
Pune–Bengaluru Expressway[131][132] | Karnataka, Maharashtra | 745 km (463 mi) |
Salem–Chengapalli Expressway | Tamil Nadu | 103 km (64 mi) |
Varanasi–Aurangabad–Chordaha Economic Corridor | Uttar Pradesh, Bihar | 262 km (163 mi) |
Nariman Point-Cuffe Parade Sea-Link[133] | Mumbai, Maharashtra | 1.77 km (1.10 mi) |
Versova-Virar Sea Link[134] | Maharashtra | 42.75 km (26.56 mi) |
Varanasi–Ranchi–Kolkata Expressway[135] | Uttar Pradesh, Bihar, Jharkhand, West Bengal | 650 km (400 mi) |
Tharad–Ahmedabad Expressway[136] | Gujarat | 214 km (133 mi) |
Total | 6,031 km (3,747 mi) |
See also
edit- Ring roads in India
- Similar rail development
- Future of rail transport in India, rail development
- List of high-speed railway lines in India
- Similar roads development
- Bharatmala
- Diamond Quadrilateral, Subsumed in Bharatmala
- Golden Quadrilateral, completed national road development connectivity older scheme
- National Highways Development Project, Subsumed in Bharatmala
- North–South and East–West Corridor, Subsumed in Bharatmala
- India–China Border Roads, Subsumed in Bharatmala
- Setu Bharatam, river road bridge development in India
- Char Dham Highway, a project under MoRTH
- Similar ports and river transport development
- Indian rivers interlinking project
- List of national waterways in India
- Sagar Mala project, national water port development connectivity scheme
- Similar air transport development
- Indian Human Spaceflight Programme
- UDAN, national airport development connectivity scheme
- Highways in India
- General
References
edit- ^ https://tis.nhai.gov.in/UploadGazatte/gazatte_notification.pdf
- ^ https://law.resource.org/pub/in/bis/irc/irc.gov.in.sp.099.2013.pdf
- ^ https://www.indiacode.nic.in/bitstream/123456789/1651/1/AAA1956____48.pdf
- ^ https://nhai.gov.in/assets/pdf/highway%20rating%20notice-with%20Attachements.pdf
- ^ "Mumbai-Nagpur Expressway: CM Shinde, Dy CM Fadnavis Launch Phase-2 of Samruddhi Mahamarg". 26 May 2023.
- ^ "Bharat Mala: PM Narendra Modi's planned Rs 14,000 crore road from Gujarat to Mizoram", The Economic Times, New Delhi, 29 April 2015, archived from the original on 2 May 2015
- ^ "Government to infuse massive Rs 7 trn to build 83,677 km of roads over 5 years". The Financial Express. 30 October 2017. Retrieved 20 July 2020.
- ^ "Bharatmala Phase-I". Ministry of Road Transport and Highways (India).
- ^ "Bharatmala Pariyojana – A Stepping Stone towards New India". National Portal of India. Retrieved 18 January 2018.
- ^ a b "Brownfield National Highway Project". CEPT. Retrieved 2 August 2022.
- ^ "43,000 km state roads converted to national highways in last eight years". The New Indian Express. 2 April 2022. Retrieved 2 April 2022.
- ^ "Maharashtra, UP to drive state-led capex in road sector in next 3 yrs". The Times of India. 7 May 2019. Retrieved 1 June 2019.
- ^ Dash, Dipak Kumar (23 November 2009). "By 2022, govt to lay 18,637 km of expressways". The Times of India.
- ^ Kumar, Ashutosh. "Expressway cost pegged at Rs20 crore/km". Daily News and Analysis. Retrieved 16 September 2016.
- ^ "Working to develop 200,000 km national highway network by 2025: Gadkari". business standard. Retrieved 31 January 2022.
- ^ "Govt's Vision '47 set to target 50,000km of expressways". 5 January 2024. Retrieved 4 June 2024.
- ^ a b c Bharatmala presentation
- ^ https://nhai.gov.in/nhai/sites/default/files/2020-08/Doc__3ddfd03e-c_.pdf
- ^ "Notification dated March 13, 1986" (PDF). The Gazette of India. Retrieved 12 November 2021.
- ^ "Ahmedabad Vadodara Expressway to be ready by March-Source-Business Standard". Archived from the original on 4 October 2012. Retrieved 30 December 2021.
- ^ "Notification dated March 30, 2006" (PDF). The Gazette of India. Retrieved 12 November 2021.
- ^ "Gurgaon: Kundli-Manesar expressway inauguration today". Retrieved 5 November 2018.
- ^ "Notification dated June 18, 2020" (PDF). Archived (PDF) from the original on 29 May 2022. Retrieved 24 September 2020.
- ^ "Delhi-Meerut Expressway open for public, cuts travel time to 45 minutes".
- ^ Notification dated 10 January 2020
- ^ "Notification dated June 25, 2020" (PDF). Archived (PDF) from the original on 3 May 2021. Retrieved 24 September 2020.
- ^ "Notification dated December 15, 2020" (PDF). The Gazette of India. Retrieved 12 November 2021.
- ^ "Notification dated January 1, 2021" (PDF). Archived (PDF) from the original on 21 April 2021. Retrieved 21 April 2021.
- ^ "Jaipur–Bandikui e-way to be completed by November '24". The Times of India. 23 December 2023. ISSN 0971-8257. Retrieved 24 May 2024.
- ^ "Nitin Gadkari's ambitious infrastructure plan: 5 new greenfield highways to come up on major routes". The Financial Express. 14 May 2018. Retrieved 2 September 2018.
- ^ "Work allotted for six-laning of Ludhiana-Bathinda expressway". Tribuneindia News Service. Tribune News Service. Retrieved 12 July 2022.
- ^ "Raipur Visakhapatnam Expressway Route Map, Cost, Progress, and More - Infra Info Hub". 28 January 2024. Retrieved 3 February 2024.
- ^ "Welcome to DND Flyway". Dndflyway.com. 22 July 2009. Archived from the original on 2 October 2011. Retrieved 16 July 2010.
- ^ "Excess cars made tolling a taxing truth at first: Expressway builder". Express India. Archived from the original on 20 November 2008. Retrieved 16 September 2015.
- ^ "Delhi-Panipat Expressway (NH-44) : Finally पूरा बन कर तैयार 🤩 #detoxtraveller". Detox Traveller. 26 June 2023.
- ^ "Delhi Faridabad Expressway". Archived from the original on 1 January 2016.
- ^ "Badarpur flyover to open today". The Times of India. 5 October 2010. Archived from the original on 10 July 2012.
- ^ "Delhi Dehradun Expressway Route Map, Cost, Progress and More - Infra Info Hub". 23 June 2024. Retrieved 2 July 2024.
- ^ "Bengaluru-Vijayawada Expressway Route, Map, Cost, Progress, Benefits and More - Infra Info Hub". 9 August 2024. Retrieved 9 August 2024.
- ^ "Surat Chennai Expressway Route Map, Cost, Progress, and More - Infra Info Hub". 23 May 2024. Retrieved 30 May 2024.
- ^ "Development of Highway sector in MP: Centre incorporates Atal Progress-Way in Bharatmala Pariyojana Phase-1".
- ^ "शुरू हुआ 6 लेन एक्सप्रेसवे का निर्माण, हरियाणा, यूपी सहित 4 राज्यों को होगा फायदा, एक घंटा घट जाएगा सफर". 2 August 2023.
- ^ "Construction of Nagpur-Vijayawada Express Highway is speeding up - Sakshi".
- ^ "Nagpur Vijayawada Expressway Route, Progress, Benefits, and More - Infra Info Hub". 2 July 2024. Retrieved 2 July 2024.
- ^ "Trans Haryana Expressway - Ambala-Narnaul Expressway - NH 152D Route Map, Connectivity, and More. - Infra Info Hub". 27 May 2024. Retrieved 30 May 2024.
- ^ "The 10 Amazing Expressways in India". www.walkthroughindia.com. 25 March 2011. Retrieved 12 November 2021.
- ^ "Amas Darbhanga Expressway Route Map, Cost, Progress, and More - Infra Info Hub". 1 July 2024. Retrieved 10 July 2024.
- ^ "Panipat-Dabwali Expressway to connect Uttar Pradesh, Haryana with THESE states; reduce travel time to Karnal". DNA India. Retrieved 12 February 2023.
- ^ "Union Minister Nitin Gadkari shares stunning images of Ranchi-Jamshedpur Expressway". 28 August 2023.
- ^ "Nitin Gadkari inaugurates, lays foundation stone for nine projects in Jamshedpur". The Economic Times. 23 March 2023.
- ^ a b "New 6-lane Ranchi-Jamshedpur Expressway to boost connectivity and economy in Jharkhand - Rise Ranchi". 28 August 2023.
- ^ "Ahmedabad Dholera Expressway Route Map, Cost, Progress, and More - Infra Info Hub". 9 January 2024. Retrieved 29 January 2024.
- ^ "Indore Bhopal Expressway: Bhopal to Indore in two hours, along with an industrial corridor will be built; 70 m width will be". 16 December 2022.
- ^ "Chennai Port-Maduravoyal corridor to have 6 lanes". The Hindu. 15 March 2018. Retrieved 30 May 2018.
- ^ "Chennai Port to Maduravoyal corridor project in TN to be completed by Dec 2024, says Union Minister Nitin Gadkari". News On AIR. 3 October 2022. Retrieved 13 March 2023.
- ^ "MoRTH invites bids for ₹3,200-cr Gazipur-Ballia highway". 12 August 2022. Retrieved 12 August 2022.
- ^ "UPEIDA to acquire land for Ghazipur-Manjhighat greenfield highway". The Metro Rail Guy. Retrieved 12 July 2022.
- ^ "Sonipat To Jind सिर्फ 50 मिनट में: नवंबर से NH 352A पर दौड़ेंगे वाहन, 799 करोड़ की लागत से हो रहा निर्माण". Amar Ujala (in Hindi). Retrieved 24 May 2024.
- ^ "Mumbai-Pune expressway 'missing link' project 60% over, to have Asia's widest tunnel". 10 November 2022.
- ^ "PIB Foundation stone for Phase II of Chennai Bypass". PIB. Archived from the original on 28 September 2007. Retrieved 25 February 2017.
- ^ "Panipat elevated highway inaugurated". Projectsmonitor.com. Archived from the original on 14 January 2010. Retrieved 16 July 2010.
- ^ "Ludhiana: Finally, elevated highway complete, inclement weather delays opening". 26 January 2024. Retrieved 4 June 2024.
- ^ "पूर्वांचल के इन जिलों को बड़ा तोहफा, मार्च से शुरू होगा रिंग रोड फेज-2 का निर्माण". Patrika News. 16 January 2018. Retrieved 12 November 2021.
- ^ "NHAI plans to develop Model Stretches in every state". www.outlookindia.com. Retrieved 12 November 2021.
- ^ "Another Outer Ring Road stretch to be opened today". TOI. Retrieved 16 July 2010.
- ^ "Longest Elevated Expressway inaugurated in Hyderabad | India Trends". Indiatrends.info. 20 October 2009. Archived from the original on 21 July 2011. Retrieved 16 July 2010.
- ^ "Hyderabad gets India's longest flyover". NDTV. Retrieved 16 July 2010.
- ^ https://timesofindia.indiatimes.com/city/nagpur/samruddhi-mahamarg-cm-fadnavis-iconic-project-set-for-completion-in-january-2024/articleshow/116018215.cms
- ^ "'Golden Triangle' : Ranchi-Dhanbad-Jamshedpur Expressway on the Anvil – Jharkhand Mirror". 27 November 2017.
- ^ "PM Modi to inaugurate 340-km long Purvanchal Expressway on Nov 16 | Check out spectacular photos". Retrieved 12 November 2021.
- ^ "IAF fighter planes to welcome inauguration". Nyooz. Archived from the original on 13 January 2017. Retrieved 23 February 2017.
- ^ "Facts About Yamuna Expressway". Projects Jugaad. 5 October 2013. Archived from the original on 2 December 2013. Retrieved 6 December 2013.
- ^ "Yamuna Expressway Project". Yamuna Expressway Industrial Development Authority. Archived from the original on 7 December 2013. Retrieved 6 December 2013.
- ^ "Noida: An idea that has worked". The Times of India. 4 June 2003.
- ^ "Ganga Expressway: Know Route Map, Progress and Latest Updates - Infra Info Hub". 23 December 2023. Retrieved 28 January 2024.
- ^ "Gorakhpur link expressway". Retrieved 14 November 2019.
- ^ "डेवलपमेंट में बाधा: उज्जैन-गरोठ फोरलेन से सड़कें कनेक्ट नहीं होंगी; 2100 करोड़ रुपए से बनने वाली रोड का विसंगति पूर्ण प्लान - Ujjain News". Dainik Bhaskar (in Hindi). 17 February 2022. Retrieved 5 June 2024.
- ^ "UP pushes work on link eway network". The Times of India. 23 July 2024.
- ^ https://avenuemail.in/nitin-gadkari-to-lay-foundation-for-roads-in-khunti-today/
- ^ https://economictimes.indiatimes.com/news/politics-and-nation/north-south-road-to-airport-gets-lgs-nod/articleshow/59450640.cms
- ^ "Sewri Worli connector project faces rehabilitation challenges, MMRDA plans height increase as solution". 22 March 2024.
- ^ https://themetrorailguy.com/nhai-bareilly-ludhiana-economic-corridor-route-map-status-update/
- ^ "Agra Gwalior Expressway Route Map, Cost, Progress, Benefits and More - Infra Info Hub". 17 May 2024. Retrieved 30 May 2024.
- ^ "मगध से मिथिला को जोड़ेगा बिहार का पहला ग्रीन फील्ड एक्सप्रेस-वे, जानें कब तक बन कर होगा तैयार, कितने जिलों से गुजरेगी?". Prabhat Khabar – Hindi News. 7 March 2021. Retrieved 12 November 2021.
- ^ "CM Yogi Adityanath OKs link expressway to connect Ballia, Ghazipur". The Times of India. 27 December 2020.
- ^ a b c "Five new expressways to come up in State".
- ^ "4 Bidders for Bhandara – Gadchiroli Expressway's Construction in Maharashtra". The metro rail guy. 14 May 2024. Retrieved 5 July 2024.
- ^ "Changing City: An elevated corridor that is set to be gamechanger in travelling from Mumbai to Pune". 10 March 2023.
- ^ a b "Bihar set to get its 4th expressway, will connect Gorakhpur to Siliguri". Hindustan Times. 23 November 2021. Retrieved 24 November 2021.
- ^ "Faster connectivity from Hisar to Delhi". The Times of India. 9 March 2018. Retrieved 9 March 2018.
- ^ "After Samruddhi Mahamarg, Maharashtra shifts focus on Alibaug-Virar Multi Modal Corridor". The Indian Express. 21 December 2022. Retrieved 23 December 2022.
- ^ "Ghaziabad–Kanpur Expressway: Ghaziabad to Kanpur in 3.5 hrs, work on four-lane project to begin on". DNA India. 21 December 2022. Retrieved 11 November 2023.
- ^ "Proposed Alignment" (PDF). Archived from the original (PDF) on 30 June 2020. Retrieved 10 July 2020.
- ^ "Ganga e-way alignment plans ready for UP CM's nod before consultant invite | Lucknow News – Times of India". The Times of India. 18 September 2019. Retrieved 12 November 2021.
- ^ "7 bids for Upper Ganga Canal Expressway". Financialexpress.com. 11 March 2010. Retrieved 16 July 2010.
- ^ "No state consent, NHAI goes ahead with four-laning of highway section". Indian Tollways. 3 December 2009. Archived from the original on 6 December 2009. Retrieved 16 July 2010.
- ^ "NOTICE INVITING TENDER" (PDF). MAHARASHTRA STATE ROAD DEVELOPMENT CORPORATION LIMITED, MUMBAI(A Govt. of Maharashtra Undertaking). Retrieved 12 October 2022.
- ^ "With Samruddhi Expressway Nearing Completion, Maharashtra Begins Work On 2 New Expressways Connecting Pune-Nashik, Nagpur- Goa". India Infra Hub. 18 October 2022. Retrieved 18 October 2022.
- ^ "Pune Aurangabad Expressway Route Map, Cost, Progress, and More - Infra Info Hub". 25 June 2024. Retrieved 10 July 2024.
- ^ "Gorakhpur Siliguri Expressway Route, Map, Progress and More - Infra Info Hub". 31 July 2024. Retrieved 31 July 2024.
- ^ "NHAI chalks out plan to build 22 greenfield expressways by FY25". Construction Week India. 22 January 2020. Retrieved 4 June 2020.
- ^ "Pune: Maharashtra Government Approves HCMTR Corridor to Enhance City Transportation". 18 June 2024. Retrieved 29 June 2024.
- ^ a b "23 new expressways and highways coming up in next 5 years". The Times of India. 13 August 2020. Retrieved 13 August 2020.
- ^ a b "2 coastal road projects for a seamless link to Navi Mumbai airport and beyond". Hindustan Times. 2 February 2024. Retrieved 24 May 2024.
- ^ "Mysuru-Kushalnagar four-lane Expressway: 11 firms bid for tender". 5 March 2023.
- ^ "Nagpur-Gondia Expressway – Information & Status". The metro rail guy. 23 May 2024. Retrieved 5 July 2024.
- ^ "Nagpur – Chandrapur Expressway – Information & Status". The metro rail guy. 23 May 2024. Retrieved 5 July 2024.
- ^ Ramakrishnan, N (3 January 2018). "Feedback Infra pitches for a big role in designing greenfield expressways". Business Line. Archived from the original on 31 May 2018. Retrieved 31 May 2018.
- ^ "All about Nagpur – Goa Expressway". Times Property. 15 February 2023. Retrieved 11 March 2023.
- ^ "Nagpur Goa Expressway Route Map, Cost, Progress, and More - Infra Info Hub". 30 May 2024. Retrieved 30 May 2024.
- ^ "These expressways will shorten the distances in Uttar Pradesh". The Times of India. Retrieved 6 December 2019.
- ^ a b c d "Uttar Pradesh: Yogi Govt Plans Six More Expressways, To Connect Major Hindu Religious Cities". The Hindu. India Infra Hub. 21 September 2022. ISSN 0971-751X. Retrieved 21 September 2022.
- ^ "Tharad - Ahmedabad Expressway – Information & Status Update".
- ^ "Mumbai: BMC plans Rs 16,621 crore Coastal Road extension linking Versova to Dahisar". The Times of India. 5 August 2023.
- ^ "Madhya Pradesh: It will connect Bhopal and Singrauli via Damoh, Katni, Rewa, Sidhi". The Hindu. India Infra Hub. 15 February 2023. ISSN 0971-751X. Retrieved 15 February 2023.
- ^ "Centre approves Chambal, Narmada Expressways in MP". The Times of India. Retrieved 8 October 2017.
- ^ "Narmada Expressway Route Map, Cost, Progress, and Latest Updates - Infra Info Hub". 26 July 2024. Retrieved 30 July 2024.
- ^ "Outer ringroad for Amaravathi". The Times of India. 8 December 2015. Retrieved 8 December 2015.
- ^ Jisha Surya (30 March 2018). "Outer ring road for capital to become a reality soon". The Times of India. Retrieved 15 April 2022.
- ^ "UPEIDA".
- ^ "Development of Purvanchal Expressway" (PDF). Retrieved 12 November 2021.
- ^ Sood, Jyotika (9 July 2018). "Govt may launch 7 greenfield projects under Bharatmala". Mint. Retrieved 13 July 2018.
- ^ "Raipur-Vizag Expressway Proj under Bharatmala Project: Centre". The Pioneer. Retrieved 4 August 2018.
- ^ "bharatmala-2-0-to-focus-on-expressways-add-4000-km-greenfield-roads". The Times of India. January 2019. Retrieved 2 January 2019.
- ^ "Bareilly-Gorakhpur Expressway – Information & Status".
- ^ Shah, Jay (27 July 2024). "Chennai Salem Expressway Route Map, Cost, Progress, and More". Retrieved 30 July 2024.
- ^ "यूपी में ये 10 ग्रीनफील्ड एक्सप्रेसवे बदल देंगे प्रदेश की सूरत, होगा 1.38 लाख Cr. का निवेश-Greenfield Expressways in UP".
- ^ "Terai Expressway: सामरिक दृष्टि से अहम होगा 700 KM लंबा गोरखपुर- शामली एक्सप्रेसवे, उतर सकेंगे लड़ाकू विमान".
- ^ "Gorakhpur Shamli Expressway Route Map, Cost, Progress, and More - Infra Info Hub". 25 May 2024. Retrieved 30 May 2024.
- ^ "NHAI ने दी मंजूरी- अजमेर-जालंधर ग्रीनफील्ड के लिए 4 जिलों में होगी भू-अवाप्ति". Dainik Bhaskar (in Hindi). Retrieved 2 September 2018.
- ^ "Bharatmala 2.0". TOI. Retrieved 21 January 2019.
- ^ "Pune Bangalore Expressway Route Map, Cost, Progress, and More - Infra Info Hub". 17 June 2024. Retrieved 2 July 2024.
- ^ Shah, Jay (5 July 2024). "Nariman Point-Cuffe Parade Sea Link". Retrieved 13 July 2024.
- ^ "On the Map: How Mumbai is Redrawing Its Road Transit with a 200 Km Network of Sea Links and Bridges". 26 January 2024.
- ^ "Varanasi Kolkata Expressway Route Map, Cost, Progress, and More - Infra Info Hub". 21 January 2024. Retrieved 28 January 2024.
- ^ "Tharad Ahmedabad Expressway Route Map, Progress and More - Infra Info Hub". 17 April 2024. Retrieved 30 May 2024.