The Cross Tay Link Road is a road-construction project in Perth and Kinross, Scotland. It will link the A93 and A94 roads, near Scone, to the A9 north of the Inveralmond Roundabout, at Perth, via a new stretch of road, 3.7 miles (6.0 km) long.[1] It will involve a three-span bridge over Scotland's longest river, the Tay,[2] hence the project's name. A cycle path will run parallel to the bridge's carriageway.[1]

The link road will connect to this section of the A9, north of the Inveralmond Roundabout

The project, which is expected to cost £118 million,[3] is the second phase of the Perth Transport Futures Project, which was formed to "address the key issues identified in the Perth Traffic and Transport Issues Scottish Transport Appraisal Guidance".[4]

Perth & Kinross Council (PKC) stated that the project would "unlock key development land".[5]

Study

edit
 
 
Inveralmond Roundabout
Location of the Inveralmond Roundabout in Perth and Kinross

A 2010 study predicted that traffic increases would exceed Perth's capacity, while also highlighting physical limitations caused by local geography (such as Kinnoull Hill and the River Tay) and existing infrastructure (such as the Highland Main Line railway). An assessment, completed in 2016, selected a corridor to the north of the city that should be taken into consideration for the purpose of traffic remediation. The route was approved at a meeting of Perth and Kinross Council (PKC) in December 2016.[4]

It is the first major road project in the vicinity of Perth since the construction of the Friarton Bridge, which was completed in 1978, and it will be the largest to date.[3]

Objective

edit

According to Sweco, the Swedish engineering consultation company, the project will help reduce traffic congestion in Perth's city centre, particularly on the A989 (the city's Inner Ring Road) and in Bridgend, on the eastern side of the River Tay. It is also expected to promote sustainable travel.[4]

Environmental impact

edit

Sweco acknowledges that the construction methods that are necessary in all facets of the project pose environmental risks. As a result, the construction process will be an important part of the environmental impact assessment.[4]

Opponents of the project, in particular the residents of Scone, believe it will have a "devastating impact" on the countryside.[1]

Ramblers and the Scottish Rights of Way and Access Society voiced disapproval that several core paths will be closed during the construction process.[1]

The ecology at the Highfield Plantation Woodland, north of Scone, will be given its own "green bridge" to safely cross the new construction.[3][6][7]

Concern was expressed at the predicted increase in traffic through local villages.[8]

Timeline

edit

The proposed start date of the project was late 2021, with an expected completion date of 2024;[4] preparatory work did not begin until late January 2022, however.[9][1]

In June 2022, it was announced that a 50-mile-per-hour (80 km/h) speed limit would be in place on a four-mile stretch of the A9 for eighteen months.[2]

A further increase in costs was approved by PKC councillors in September 2022.[10]

Surrey-based BAM Nuttall were appointed the contractors for the project in 2021.[1]

John Swinney, the local MSP and First Minister of Scotland, visited the project site in August 2024; at this time the 'Destiny Bridge' over the Tay was nearing completion.[11]

References

edit
  1. ^ a b c d e f Robertson, Aileen. "Bulldozers to move in as work on Perth's Cross Tay Link Road begins". The Courier. Retrieved 2022-07-01.
  2. ^ a b Chalmers, Robbie (2022-06-21). "Four-mile stretch of A9 near Perth to be under 50mph speed limit for 18 months". Daily Record. Retrieved 2022-07-01.
  3. ^ a b c "Advance work to begin for £118m Cross Tay Link Road". Scottish Construction Now. Retrieved 2022-07-01.
  4. ^ a b c d e Sweco (2019-11-13). "Cross Tay Link Road - Non- Technical Summary". ArcGIS StoryMaps. Retrieved 2022-07-01.
  5. ^ Cargill, Paul (2022-01-25). "Preparatory work on new Cross Tay Link Road in Perthshire to start this week". Daily Record. Retrieved 2023-06-12.
  6. ^ "#GetOutside: do more in the British Outdoors". OS GetOutside. Retrieved 2022-07-01.
  7. ^ Chalmers, Robbie (2022-04-20). "Disruption concerns raised at Cross Tay Link Road consultation in Scone". Daily Record. Retrieved 2022-07-01.
  8. ^ Robertson, Aileen (2021-07-15). "Cross Tay Link Road: Figures show single track Perthshire road will become rat run". The Courier. Retrieved 2023-06-12.
  9. ^ "Advance work to begin for £118m Cross Tay Link Road". Scottish Construction Now. Retrieved 2022-07-01.
  10. ^ Anderson, Kathryn (2022-09-09). "Councillors approve funding up to £32.5 million more on Cross Tay Link Road". Daily Record. Retrieved 2023-06-12.
  11. ^ First Minister gets preview of Perth's new Destiny Bridge as project milestone completed, Daily Record, 15 August 2024
edit