D35 motorway (Czech Republic)

D35 motorway (Czech: Dálnice D35), formerly Expressway R35 (Czech: Rychlostní silnice R35) is a highway in the Czech Republic. Once completed, it will be the second longest highway in Czech Republic, running from Úlibice to the D1 at Lipník nad Bečvou.[1] The motorway is part of the European route E442.

D35 Motorway shield}}
D35 Motorway
Dálnice D35
Route information
Part of E442 E462
Length89 km (55 mi)
Planned: 205 km (127 mi)
Major junctions
FromÚlibice
Major intersections
To D 1 at Lipník nad Bečvou
Location
CountryCzech Republic
RegionsOlomouc, Pardubice, Hradec Králové, Liberec
Major citiesOlomouc, Hradec Králové, Liberec
Highway system

After completion, it will become an alternative route to motorway D1 between Prague and Olomouc and Ostrava. The first segment was opened in the 1970s. As of 2023, 89 km of full motorway are in operation in two segments.[2]

History

edit

Originally, the D35 motorway from Hradec Králové to Lipník nad Bečvou was planned. However, in 1987, it was decided to build the R35 expressway instead of the motorway and to extend its route to Liberec. The rest of the R35 expressway is classified as a Class I road for motor vehicles.

Currently, the section of the D35 motorway Mohelnice - Olomouc - Lipník nad Bečvou is in operation with a break near Křelov near Olomouc. A section of the former R35 Liberec - Turnov expressway is also in operation, but it has not been classified as a motorway and since 1 January 2016 has been an I/35 motorway.

On 27 November 2009, the section Sedlice - Opatovice nad Labem was put into operation with a length of approximately 3.5 km. The three-storey Opatovice interchange is one of the largest intersections in the Czech Republic. Around Hradec Králové, the D35 runs in parallel with the D11 motorway (between the Sedlice interchange and the Plotiště interchange), with the last of the interchange sections completed in December 2021.

In December 2021, the Opatovice nad Labem - Časy section of the motorway was put into operation. This, together with the opening of other sections of the D11 motorway, enabled the transfer of transit from Svitavy in the direction of Prague, Jičín and Jaroměř outside Hradec Králové. The connecting section to Ostrov was opened a year later, in December 2022.

Under construction

edit
Section Length Start of construction Completion
Hořice - Sadová 10.45 km 11/2023 planned 2025
Ostrov - Vysoké Mýto 7.0 km 05/2024 planned 2026
Ostrov - Vysoké Mýto, Homole tunnel 0.53-0.57 km 05/2024 planned 2026
Vysoké Mýto - Džbánov 5.95 km 11/2023 planned 2025
Džbánov - Litomyšl 7.95 km 04/2024 planned 2027
Janov - Opatovec 11.75 km 05/2023 planned 12/2025

Images

edit

References

edit
  1. ^ "Planned construction progress on the road and motorway network" (PDF). Road and Motorway Directorate of the Czech Republic. Retrieved 21 October 2018.
  2. ^ "Dálnice D35 (only CZ)". Archived from the original on 2015-12-27.
edit