Aditya is a solar-powered ferry operating between Vaikkom and Thavanakkadavu[2] in the Indian state of Kerala.[2][3] The boat was inaugurated by Kerala Chief Minister Sri. Pinarayi Vijayan and Central Cabinet Minister for Power, Renewable Energy, Sri. Piyush Goyal on 12 January 2017.[4]

History
India
NameAditya
OwnerKerala State Water Transport Department
OperatorKerala State Water Transport Department
Port of registryKodungallur
RouteVaikom – Thavanakkadavu
BuilderNavalt Solar and Electric Boats, Kochi, India
Cost₹2 Crores
Yard numberY-09
Launched9 November 2016
CompletedNovember 2016
In service12 January 2017
StatusIn service
General characteristics [1]
Class and typeIndian Register of Shipping IRS +IW ZONE 3 FERRY
Displacement23 tonnes
Length21 m
Beam7 m
Height3.7 m
Draught0.95 m
Depth1.75 m
DecksSingle
Installed power2 × 9 kW (cruise) 2 × 20 kW (max)
Propulsion2 Permanent magnet asynchronous electrical motors – 20 kW each (max) @ 700 rpm
Speed
  • 7.5 knots (13.9 km/h; 8.6 mph) (max)
  • 5.5 knots (10.2 km/h; 6.3 mph) (cruising)
Capacity75 passengers
Crew3
ADITYA solar boat

It is India's first solar-powered ferry[3][5] and was the largest solar-powered boat in India until Indra_(boat) was launched in 2023[6][7] The vessel was designed and built by Navalt Solar and Electric Boats[8] in Kochi, India. Navalt is a technology joint venture firm between Navgathi Marine Design and Constructions,[9] Alternative Energies[10] (France) and EVE Systems[11] (France).

In August 2020, MarineLink reported that by the end of the year the Kerala state would replace the three diesel ferries operating the same route with solar ones, mentioning that Aditya costs about US$79 per month compared to US$2867 for diesel-powered ones.[12] In three years the Aditya has saved more than 100,000 liters of diesel.[12] The State Water Transport Department of the Government of Kerala also decided to replace all of its 48 diesel ferries with solar ones.[12]

Technical features

edit

The 20-metre-long and 7-metre-wide boat is covered by 140 square metres (1,500 sq ft) of solar panels rated at 20 kW, which in turn connect to two electric motors of 20 kW, one in each hull. There are 700 kg of lithium-ion batteries in the ship's two hulls with a total capacity of 50 kWh. The catamaran hull and its shape allow it to reach speeds of up to 7.5 knots. This was verified by Indian Register of Shipping surveyor, Kerala Port surveyor and technical committee. The hull was designed based on extensive experience of Navgathi[13] and AltEn[14] and extensive computational fluid dynamics (CFD) was done to determine its hydrodynamics. The boat is designed to be used as a passenger ferry to operate between Vaikom and Thavanakadavu.[15]

The normal operating speed is 5.5 knots (10 km/h) to achieve a 15-minute travel time between Vaikom and Thavanakkadavu, a distance of 2.5 km on water. For achieving this speed, the power needed is about 16 kW. During maneuvering, when leaving the jetty or approaching it, about 22 kW of power is needed. Hence, on average about 20 kW power is needed. The total running time, neglecting the time in jetty for embarkation and disembarkation of passengers is 5.5 hours on a sunny day (depending on client needs).[16]

Although the maximum power needed is a total of 22 kW during maneuvering and 16 kW under cruise, more than double the power, a total of 40 kW, is provided in two motors of 20 kW each. The two systems on either side of the boat (in each demi-hull) are electrically independent to ensure redundancy in case of system failure in one. Even if one system fails the power is available to safely cruise to shore with others. Also, unlike diesel engines, since efficiency does not drop with load, the electric motors can normally operate at 50% load and in emergencies at 100%.[16]

For higher safety standards and reliability, the vessel is built under Indian Register of Shipping rules for inland vessels and operating conditions of the Vaikom – Thavanakkadavu route. The boat construction is complete and was tested by Technical committee, Indian Register of Shipping surveyor and Kerala Port surveyor on 16 November 2016, near in backwaters at Aroor.[16][17] The boat is registered in Kodungallur Port under Kerala Ports.

The boat is remotely monitored and troubleshooting can also be done remotely. All the operating parameters of the boat are recorded and transmitted to the NavAlt Solar and Electric Boats's server from where the technical experts can monitor the boat. The upgrades and settings in the software can also be performed remotely as if a computer is plugged into the boat. This makes the boat even safer.

The project cost was US$370,000.[16][18][19]

Awards

edit
  • Winner of the First Gussies Award for the Best Electric Ferry in the World 2020 in memory of Gustave Trouvé[20]
  • Solar Impulse Foundation Efficient Solution Label as a profitable and eco-friendly solution[21]
  • Listed in the Significant Small Ships in the World 2017,[22][5] by Royal Institute of Naval Architects, UK
  • FICCI Best R&D Project that can be scaled up (Catapult Award) 2017[23]

Safety features

edit
  • The boat is a catamaran and hence more stable than single-hulled boats. The boat can safely carry 200 passengers and still meet the tough stability criteria of IMO sea-going ships.
  • The propulsion battery is approved by DNV Class. These higher standards of safety are essential to ensure the risk of thermal runaway is minimal.
  • The battery monitoring is on a cell level and hence risks are lower.
  • There are three levels of safety warning – first being a warning that certain parameters are approaching the limit, second is the warning that limits have reached and hence need a slowdown, and finally the warning that limits have breached the upper limit and the system need to shut down to protect it. The parameters include the temperature of cells, motor, and many more.
  • There is two independent power train that provides reliability and redundancy. A system fault in one power train does not affect the other since they are electrically independent. The boat satisfies the Indian Register of Shipping's safety requirement of being able to maintain cruise speed with one set of propulsion shut down.[24]

Statistics

edit

The boat is operating since launch on 12 January 2017 between Vaikkom and Thavanakkadavu.[2][25] The numbers for this total period is as follows:

Year 7 Year 6 Year 5 Year 4 Year 3 Year 2 Year 1
No.of passengers (million) 2.23 2 1.68 1.35 1.06 0.6 0.3
Distance travelled 142,000 125,000 102,500 80,000 63,000 38,000 19,000
Diesel saved (litres) 210,000 190,000 160,000 130,000 105,000 58,000 29,000
Savings (USD) 243,000 187,500 147,500 110,000 93,750[26] 65,000 36,000
Savings (lakh INR) 200 150 118 88 75[26] 45 25
CO2 avoided (tonnes) 563 509 420 330 283[26] 156 81
NOx avoided (tonnes) 8.3 7.5 6 4.6 3.9[26] 2.2 1.1
SOx avoided (tonnes) 1.7 1.5 1.25 1 0.8[26] 0.4 .2
Particulates avoided (kg) 211 191 158 124 106[26] 59 30

The average savings in CO2 is 84.8 tonnes per year. This is equivalent to 3,856 trees if you consider 22 kg of CO2 is saved by a fully grown tree in an year.[27]

Year 1 Statistics

edit

The first year of operation shows the following summary.[28]

  • Propulsion energy per day for 22 trips – 72.8 kWh
  • Propulsion energy per trip – 3.3 kWh
  • Battery state of charge (SOC) at end of the day – 58%
  • Grid charging cost per day – 2.6 US$ (₹ 179)
  • OPEX savings – 25 Lakh rupees
     
    ADITYA daily energy consumption[28]

The Government of India under the leadership of Prime Minister, Sri. Narendra Modi and the Ministry of New and Renewable Energy agreed to sponsor the project considering that this is a first of its kind in India. The benefit of sponsorship would mean that Kerala State Water Transport Department would get the boat at almost free of cost. In this scenario the boat is cheaper than the conventional boat and they would start saving money from day one.[16][19] However the ministry is yet to give the subsidy amount to Kerala State Water Transport Department. Another unfulfilled demand is the equal treatment of electric boats to electric buses under FAME scheme that would have enabled 20% cost reduction in the project. NITI-Aayog is yet to remove this discrimination.

Initial Days Operation

edit

The first 150 days operation data shows that even rainy days during monsoon did not affect the schedule of the boat.[25][29]

  • Propulsion energy per day for 22 trips – 73.7 kWh
  • Propulsion energy per trip – 3.5 kWh
  • Battery state of charge (SOC) at end of the day – 60%
  • Grid charging cost per day – 2.5 US$ (₹ 163)

The first 60 days operation data of ADITYA yielded the following results[30]

  • Propulsion energy per day for 22 trips – 73.3 kWh
  • Propulsion energy per trip – 3.33 kWh
  • Battery state of charge (SOC) at end of the day – 65%
  • Grid charging cost per day – 1.9 US$ (₹ 124)

Test and trials

edit
 
Model

The boat was launched on 9 November 2016. After that multiple sets of tests and trials were conducted to verify the operational characteristics and safety standards of the boat.

  • Optimisation Trials – to refine the settings in the internal software to ensure higher efficiency in the solar energy conversion and propulsion system, the tests was done on 13 and 14 November 2016 with the experts from France.
  • Builders Trials – done on 15 November 2016, to ensure the systems were functioning as per specifications.
  • IRS and Technical Committee Trials – done on 16 November 2016[24] to verify the operation, speed, safety of the boat. The maximum speed was noted as 7.4 knots @ 90% propulsive power. The power needed to move the boat at a cruise speed of 5.5 knots was 15 kW. The boat was also tested for redundancy trials by shutting down one system and checked whether using one system the boat can still move at a cruise speed of 5.5 knots. Other maneuvering tests were also done.
  • Client Trials – done on 25 November 2016,[3][31] along with Transport Minister Sri. A. K. Saseendran, Aroor MLA Sri. A. M. Ariff, Vaikom MLA C. K. Asha. The performance was satisfactory for the dignitaries as well as the operators of the Kerala State Water Transport Department. The Transport Minister proclaimed that 14 more such ferries are planned this year.[3]
  • Site Trials – done at Vaikom to Thavanakkadavu route in presence of Technical committee, IRS and Kerala Port surveyor from morning to evening. As per the specifications, 22 trips was done with a full load and it was satisfactory.

Tender specifications

edit
 

During conceptualising the project, it was envisaged that the total energy needed to operate the ferry for 5.5 hours is 110 kWh (20 kW is average power). As 1 kW solar panels produce approximately 4 kWh of energy per day, factoring the system efficiency and standard sun of the location of 5.72 (averaged throughout the year). Hence the energy from solar panels is 80 kWh. The gap in energy is provided by lithium battery that can provide up to 40 kWh (80% discharge) from a total capacity of 50 kWh. The lithium batteries are fully charged in the morning because of overnight grid charging.[16]

A trip between the two boat points takes 15 minutes and it was estimated to need the energy of 5 kWh. Hence a total of 22 trips would be made daily transporting 1,650 people daily, or 580,000 people every year without burning fuel.

Trips on average sunny day: 7:00 AM to 7:00 PM (running hours 5.5 hours).

The below table describes the prediction for 22 trips in each column, and for each trip the start time and end time. It also lists the break time at the end of each trip. In non-peak hours this is about 15 minutes, in peak time it is 10 minutes and around noon it is two hours. The energy from the sun is cumulative at the end of the period and for an average sunny day it is about 72 kWh from 18 kW panels (the rest is for auxiliary systems and charges a different battery bank). The battery state of charge (SOC) is shown at the beginning of the trip and end of the trip. At the end of the day, the battery has about 20% charge left. The energy use can be further optimised by adding one more trip (5 kWh usage) so that end of day battery SOC can be 10%.

On a bright sunny day, the no. of trips can be increased by taking trips from 11:55 to 14:05 break. About four more trips can be made in this period.

On a cloudy day, the no. of trips is reduced and the break time is increased. If it is very cloudy during the break time, then shore charging can be done. This is a 32A charger and charges at 7 kW. Hence in the three-hour break, it can charge the battery by 21 kWh. With two upcoming landmark projects, NavAlt boats will be foraying into the fishing sector and defence industry for the first time.[32]

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Vaikom 7:00 7:45 8:00 8:40 8:50 9:30 9:40 10:25 10:40 11:25 13:35 14:20 14:35 15:20 15:35 16:20 16:30 17:10 17:20 18:00 18:15 19:00
Thavanakadavu 7:15 7:30 8:15 8:25 9:05 9:15 9:55 10:10 10:55 11:10 13:50 14:05 14:50 15:05 15:50 16:05 16:45 16:55 17:35 17:45 18:30 18:45
Break 0:15 0:15 0:10 0:10 0:10 0:10 0:15 0:15 0:15 2:10 0:15 0:15 0:15 0:15 0:15 0:10 0:10 0:10 0:10 0:15 0:15
Total Time 0:30 0:30 0:25 0:25 0:25 0:25 0:30 0:30 0:30 2:25 0:30 0:30 0:30 0:30 0:30 0:25 0:25 0:25 0:25 0:30 0:30 0:15
Battery SOC (kWh) at start 50 45 40 35.5 31.7 28.8 26.5 25.5 25.2 25.5 26.1 49.3 49.3 48.7 47.3 45 41.4 35.1 27.1 22.1 22.1 17.1
Sun Production (kWh) 0 0 0.5 1.7 3.8 6.5 10.5 15.2 20.5 26.1 54.3 59.3 63.7 67.3 70 71.4 72.1 72.1 72.1 72.1 72.1 72.1
Motor consumption (kWh) 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110
Battery SOC (kWh) at end 45 40 35.2 31.1 27.9 25.3 23.4 22.8 22.8 23.3 24.1 46.8 46.6 45.6 43.8 40.9 36.9 32.1 27.1 22.1 17.1 12.1

See also

edit

References

edit
  1. ^ "Technical Data Sheet". NavAlt. Archived from the original on 5 July 2010.
  2. ^ a b c "India's first solar boat launched in Kochi". DeccanChronicle.com. 13 January 2017. Retrieved 9 February 2017.
  3. ^ a b c d "First solar ferry ride a success". Deccan Chronicle. 26 November 2016. Retrieved 26 November 2016.
  4. ^ "Kerala Govt. Commissions India's First Solar-Powered Boat, Paves the Way for a Greener Tomorrow". The Better India. 11 May 2016. Retrieved 24 May 2016.
  5. ^ a b "ADITYA, India's first solar powered ferry". Significant Small Ships of 2017: 6–8.
  6. ^ "SWTD launches 'India's largest solar-electric ferry'". The Hindu. 22 April 2016. Retrieved 15 August 2024.
  7. ^ "Kerala company builds country's largest solar ferry". timesofindia-economictimes. 22 April 2016. Archived from the original on 1 May 2016. Retrieved 24 May 2016.
  8. ^ NavAlt Solar and Electric Boats
  9. ^ Navgathi Marine Design and Constructions
  10. ^ Alternative Energies
  11. ^ EVE Systems
  12. ^ Navgathi
  13. ^ AltEn
  14. ^ "NavAlt Spreading Ripples of Eco-friendliness". Destination Kerala. Archived from the original on 9 July 2016. Retrieved 10 July 2016.
  15. ^ a b c d e f "Solar Today – India's first magazine dedicated to the emerging Solar industry". www.solartoday.co.in. Retrieved 3 July 2016.
  16. ^ "Indian Express".
  17. ^ TK, Sreeraj (5 March 2016). "Kerala's Backwaters Will Soon Have India's First Solar Powered Boats". ScoopWhoop. Retrieved 24 May 2016.
  18. ^ a b "Solar-powered ferry to debut in sunlit Kerala". India Climate Dialogue. 30 May 2016. Retrieved 3 July 2016.
  19. ^ "Winners of The 1st Gussies Electric Boat Awards". Plugboats.
  20. ^ "Solar Impulse Efficient Solutions Label". Solar Impulse.
  21. ^ "Significant Small Ships of World 2017". RINA, UK.
  22. ^ "FICCI R&D Catapult Award". FICCI.
  23. ^ a b "Solar ferry undergoes successful trials". The Hindu. 20 November 2016. Retrieved 20 November 2016.
  24. ^ a b "India's first solar boat 'Aditya' successfully completes 150 days of voyage". Deccan Chronicle. 15 June 2017. Retrieved 15 June 2017.
  25. ^ a b c d e f "3 Years of Statistics of ADITYA from Navalt Website". Navalt. 17 December 2019.
  26. ^ "European Environment Agency". European Environment Agency. 16 November 2023. Retrieved 16 November 2023.
  27. ^ a b "Economics of Aditya – India's First Solar Ferry" (PDF). IEEE India Info. 13 (3). July–September 2018.
  28. ^ "ADITYA – 150 Days of Service; and Surprise!". Sandith Thandasherry. 13 June 2017. Retrieved 5 December 2017.
  29. ^ "ADITYA – Sixty days of Operation". 25 March 2017. Retrieved 4 September 2017.
  30. ^ "Commuters, get ready for more sun-kissed rides on the waters". New Indian Express. 26 November 2016. Retrieved 26 November 2016.
  31. ^ Indian Defence News (16 December 2020). "After Aditya's success, NavAlt to venture into fishing and defence". The Indian Hawk. Retrieved 16 December 2020.
edit