The Guangzhou–Shenzhen–Hong Kong Express Rail Link (XRL), also known as the Guangshengang XRL, is a high-speed railway line that connects Guangzhou and Hong Kong (Kowloon) via Shenzhen.

Guangshengang XRL
MTR Vibrant Express Train G6581 at Guangzhou South on the inaugural day of operations along the Hong Kong section of the Express Rail Link
Overview
Native name广深港高铁
廣深港高鐵
StatusOperational
Owner
LocaleSouth China
Termini
Stations7
WebsiteOfficial website
Service
TypeHigh-speed rail line
SystemChina Railway High-speed China Railway High-speed
Services
Operator(s)
History
Opened23 September 2018; 6 years ago (2018-09-23)
Technical
Line length142 km (88.23 mi)
Number of tracksDouble-track
Character
  • Underground (Shenzhen North ↔ West Kowloon)
  • Elevated (Guangzhou South ↔ Shenzhen North)
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Minimum radius5,000–7,000 m (3.1–4.3 mi; 16,000–23,000 ft) (Guangzhou South - Shenzhen North)
2,800–3,500 m (1.7–2.2 mi; 9,200–11,500 ft) (Shenzhen North - Hong Kong West Kowloon)
Electrification25 kV 50 Hz AC (Overhead line)
Operating speed
  • 350 km/h (217 mph) (Guangzhou South ↔ Shenzhen North)[1]
  • 200 km/h (124 mph) (Shenzhen North ↔ West Kowloon)[1]
SignallingCTCS Level 3 CBTC[2]
Maximum incline1.2% (Normal)
2.0% (Difficult terrain)
Average inter-station distance20.3 km (12.6 mi)
Chinese name
Simplified Chinese广深港高速铁路
Traditional Chinese廣深港高速鐵路
Transcriptions
Standard Mandarin
Hanyu PinyinGuǎng–Shēn–Gǎng Gāosù Tiělù
Yue: Cantonese
Yale Romanizationgwóng sām góng gōu chūk tit louh
JyutpingGwong2 Sam1 Gong2 Gou1 Cuk1 Tit3 Lou6
Alternative Chinese name
Simplified Chinese广深港客运专线
Traditional Chinese廣深港客運專線
Transcriptions
Standard Mandarin
Hanyu PinyinGuǎng–Shēn–Gǎng Kèyùn Zhuān Xiàn
Yue: Cantonese
JyutpingGwong2–Sam1–Gong2 Haak3wan6 Zyun1 Sin3
Route map



Route of Guangzhou–Shenzhen–Hong Kong XRL
(Guangshen section in red and
Hong Kong section in blue)

km
0
Guangzhou South Guangzhou Metro
Guangzhou Motor Depot
Shawan Shuidao
31
Qingsheng Guangzhou Metro
50
Humen Dongguan Rail Transit
86
Guangmingcheng
Gaofeng Reservoir
Shenzhen EMU Depot
Shenzhan HSR (under construction)
102
Shenzhen North Shenzhen Metro
110
Futian Shenzhen Metro
Shek Kong sidings
142
West Kowloon
km

Only transfers with rapid transit
systems are marked in this diagram

Three types of rolling stock that operate along the XRL: Hexie (Harmony) and Fuxing (Rejuvenation) operated by China Railway, and Vibrant Express by MTR Corporation.

The first phase, Shenzhen NorthGuangzhou South, commenced revenue operation in December 2011. Services were extended to the city centre of Shenzhen at Futian in December 2015. The final phase, which connects Shenzhen-Futian to Hong Kong (West Kowloon) was inaugurated on 22 September 2018.[3][4] It opened for public on Sunday 23 September 2018.[5]

Journey times

edit
  • Hong Kong (West Kowloon) – Futian: 14 minutes (fastest)
  • Hong Kong (West Kowloon) – Shenzhen North: 18 minutes (fastest)
  • Hong Kong (West Kowloon) – Guangzhou South: 46 minutes (fastest)

History

edit

Background

edit

The railway connecting the mainland China has been important for Hong Kong since the 20th century. After the establishment of the People's Republic of China, three railway lines from the mainland, also known as “santang kuaiche” (three cargo express trains), were arranged to transport fresh food every day to maintain the daily needs of the Hong Kong people.[6] A high-speed railway connecting Guangzhou, Shenzhen and Hong Kong, railway was brought up in the late 1990s by the Government of Hong Kong. This Regional Express Railway (RER) proposal was developed in the 1994 “Railway Development Study” (RDS); it foresaw a continual growth of Hong Kong's population over the next two decades and strong demand for cross-border passenger traffic. The Hong Kong (SAR) Government commissioned a second Railway Development Study in March 1998.[7] The Study went further on the British proposal of connecting Hong Kong and China from Kowloon. The RER could be further extended to Hong Kong Island. At the same time, the report recommended that Hung Hom station should continue to play a central role in Hong Kong's mass transit. Since the typical timeframe for rail projects, from conception to completion phase, would take eight or nine years, the Railway Development Study recommended that the Hong Kong (SAR) Government should commence as soon as possible, so that the new express railway could be constructed in time to meet capacity demands.

Maglev proposal

edit

In September 1999, the then mayor of Guangzhou, Lin Shusen, announced his “Suigang maglev rail project” at the "Fortune Global Forum" in Shanghai. Lin was already working with then-Chief Executive of Hong Kong, Tung Chee-hwa, on the development of Hong Kong Disneyland. Lin proposed that a maglev railway between Guangzhou and Hong Kong would benefit visitor numbers. The cost of construction was to be borne in equal proportion by governments of both cities.[8]

Railway Development Strategy 2000

edit

The Hong Kong government, based on the results of the Second Railway Development Study by the Department of Transportation, issued a new plan, “Railway Development Strategy 2000 – new railway strategy”. On 16 May's Legislative Council meeting, the Legco Panel on Transport Railway Development Strategy tabled the strategy for use by the Hong Kong (SAR) Government. The Executive Council (upper house) recommended that, under the Chief Executive's advice, Hong Kong should adopt the "Railway Development Strategy 2000" until a further review in 2016.

 
Proposed options for Regional Express Railway

Regional Express Railway

edit

“Railway Development Strategy 2000” recommended new six new rail corridors, through the New Territories, connecting the East Rail or the West Rail line to the border, operating between Hung Hom and the border in an express manner similar to Hong Kong Airport's Airport Express line. " The decision to build a “Regional Express”, depended on the Lok Ma Chau Spur provided additional transport capacity which would soon be saturated. According to the 1998 price estimates, construction of the RER needed a budget of about HK$130 to 170 billion.[9][clarification needed] It was intended that this railway would be operated by the Kowloon-Canton Railway Corporation or the Mass Transit Railway Corporation, depending on the location of the downtown terminal.

At that time about the “Regional Express” concept, was not a high-speed rail, but only a commuter line connecting the city and the border with “rapid rail” services, in addition to the idea of a small number of intermediate stations being set up alongside the route, but also allowing for Hong Kong and China Intercity trains to run, reducing the load on the existing East Rail line. At that time the initial alignment program has two starting points located around Hung Hom station. The first one was the Eastern scheme, a new line following the East Rail line of pink Lingnan station[clarification needed], connecting to Lo Wu station or a new rail crossings in the east of Luohu. However, this proposal needed to co-operation with the mainland. The second program for a new line from the West Rail line at Kam Sheung Road station, northwards to Lo Wu or Lok Ma Chau station.

Since 2001, the Hong Kong government began working on the “Regional Express” with mainland China, and discussing the feasibility of cooperation on “Suigang maglev rail project”. In 2001, the Hong Kong DoT, with the Shenzhen Municipal Government and Chinese railway authorities to explore the use of “RER” and maglev technology, project feasibility and actively using magnetic levitation technology to build a line from Hong Kong to Canton/Guangzhou.[10] The study pointed out that the use of a maglev train would reduce the Hong Kong to Shenzhen running time of 40 minutes to 15 minutes.[11] September 2001, when he was the Hong Kong SAR Chief Secretary Donald Tsang, visited Canton/Guangzhou, where he met with the Governor of Guangdong Province, Lu Ruihua, acting mayor of Guangzhou, Lin Shusen and Shenzhen Mayor Yu Youjun for talks about the “Regional Express line concept”.[12] Tung attended the Shanghai APEC Summit in October 2001, formally proposing the construction of a maglev railway between Canton/Guangzhou and Hong Kong Express Line plans to the State Planning Commission. The Mayor of Shenzhen Yu Youjun said at a news conference at the APEC Senior Officials' Meeting, Shenzhen and Hong Kong is planning to build maglev railway and to continue to discuss the issue.[13] But also at this time, the Guangzhou-Shenzhen Railway Co. also made a Guangzhou–Kowloon Through Train speed plan.

Switch to high-speed rail

edit

By the end of January 2002, the concept of “Regional Express” gained further development. Tsang in Beijing to attend the “Mainland and Hong Kong SAR major infrastructure coordination meeting”, and with the State Development Planning Commission and the relevant ministry officials, the talks were initially on Regional Express railway line connecting Guangzhou, Shenzhen and Hong Kong, focussing on the design and coordination of consensus between the parties. The central government officially approved research and co-ordination by the Ministry of Railways,[14][15] and officially named this railway the "Guangzhou–Shenzhen–Hong Kong Express Rail Link". With a formal agreement with the Hong Kong SAR Government, decided by the Ministry of Railways, led the establishment of an expert group to study the construction of the Regional Express high-speed rail line.[16]

In February 2002, in the framework of “collaborative meetings” by the Hong Kong SAR Government Environment, Transport and Works Bureau and the Ministry of Railways, the Guangzhou–Shenzhen–Hong Kong Express Rail Link Planning Group was established, which meant the “Railway Development Strategy 2000” planned “Regional Express” was set aside for the “Guangzhou–Shenzhen–Hong Kong Express Rail Link - Hong Kong section”. The planning Group conducted preliminary studies on the main railway necessity, function, alignment, location transit, rail technology and economic benefits.[17]

The first phase of the study topics included the functional and strategic importance of the Guangzhou–Shenzhen–Hong Kong Express Rail Link project, the relevant regional passenger transport demand analysis and forecasting, as well as railway lines and public transit locations.[18] The first phase of the study completed in September 2002[19] and reported on the September 20th 2002 at the Second “Mainland and Hong Kong's major infrastructure cooperation held meeting”. At the meeting, the high-speed rail planning team reported the first phase of on the planning for the GZ-SZ-HK XRL. Including the necessities of GZ-SZ-HK XRL construction, function and regional transportation needs, forecasting and route traffic in order to determine the strategic value of the railway.[20] Experts in Hong Kong and mainland China reached a consensus after comparing different alignments, shortlisting two options, “Guangzhou East – Dongguan – Lin Tong – Hong Kong” and “Panyu – Nansha – Shekou – Hong Kong”. A planning goal was to reduce Guangzhou to Hong Kong travel time from 100 minutes to less than 60 minutes. In addition, effective integration with the national high-speed rail network and the connections with the planned Pearl River Delta intercity rapid rail transit network.

The second phase of the study, included rail alignments, station locations and the Hong Kong section of the Guangzhou–Shenzhen line connections, the main technical standards, passenger flow forecasting, financial benefits. During the study, in response to the latest developments of both the overall urban planning and transportation network planning, the Ministries of Railways, Environment, Transport and Works respectively needed to consider some new ideas and make adjustments for the Hong Kong section of GZ–SZ–HK XRL project. In mainland China, the Ministry of Railways had to consider the feasibility of the PRD Intercity Rapid Rail network together with the Guangzhou–Shenzhen section of GZ–SZ–HK XRL. In Hong Kong, the government began to consider the use of the proposed North West Rail Link, Northern Link and the feasibility GZ–SZ–HK XRL Hong Kong section. Kowloon-Canton Railway Corporation and the Hong Kong Mass Transit Railway Corporation produced a consolidated joint report submitted to the Government, it was a preliminary assessment of their ideas, but also required further studies by the Environment, Transport and Works Bureau & KCRC of the Northern Link.

In the first and second phases of the study, the planning team had to investigate and compare the traditional wheel-rail and maglev technologies. Operating and maintenance costs were greater with maglev than with wheel-rail technology, The construction period of the project was expected to be longer for maglev than the wheel-rail technology solutions. Maglev was not conducive to the existing rail network and compatibility. Also with current high-speed railway operating speeds of up to 350 km/h (220 mph), the less than an hour goal was able to be achieved. Thus to reach the GZ–SZ–HK XRL's three goals, there was no need to adopt a relatively high cost and the technical difficulty of maglev technology. Thus, despite the advantages that high-speed maglev technology has, until August 2003, both sides tended to choose more mature high-speed wheel-rail plans. In other words, the "Regional Express" that was originally intended to have been conceived as a maglev train was cancelled.

In March 2003, the Guangzhou Railway Group Corporation general manager, Wú Jùnguāng, at the National People's Congress, submitted a bill that called for the construction of a Guangzhou–Shenzhen–Hong Kong Express Rail Link Passenger Line as soon as possible. The Guangzhou–Shenzhen Railway utilization has exceeded 90% and was saturated. According to the existing passenger growth rate, to 2005, the Guangzhou East to Shenzhen route would require 96-151 train pairs daily, which will greatly exceed the capacity of the line. It is difficult to meet the transportation needs of the future with the new high-speed rail showing greater potential in the pipeline.[21]

On 7 January 2004, China's State Council considered the “long-term railway network plan”, deciding to build more than 12,000 kilometers of “four vertical and four horizontal” Passenger Lines, including Hong Kong in the planning. The Guangzhou–Shenzhen section of the Guangzhou–Shenzhen–Hong Kong Express Rail Link correspondingly accelerated planning until July 2004, deciding to adopt the “Panyu – Nansha – Shekou – Hong Kong” route. The station located in Guangzhou's Panyu district would also connect with the Wuhan–Guangzhou Passenger Line.

Route

edit
 
Guangzhou South railway station east concourse

The 143 km (89 mi) route starts with a connection to the Wuguang High-Speed Railway at Guangzhou South railway station in Shibi, southern Guangzhou (Canton). From there it travels south to the same district before tunnelling eastwards underneath the Pearl River to Humen in Dongguan. It then moves south through three stations within Shenzhen and then across into Hong Kong where it arrives at West Kowloon Terminus in Kowloon.

 
Tracks towards Hong Kong at Futian railway station

This project has been divided into two sections, the Guangshen section with six stations, and the Hong Kong section, with one station.

Mainland Section

edit

Guangzhou–Shenzhen–Hong Kong Express Rail Link section of the Guangzhou–Shenzhen starts at Guangzhou South railway station and ends at Shenzhen Futian station, it is 116 km (72 mi) line length,[22] with a design speed of 350 km/h (220 mph). From there it travels south to Qingsheng before tunnelling eastwards underneath the Pearl River to Humen in Dongguan. It then moves south to Guangmingcheng, Shenzhen North and Futian(u/c) in Shenzhen.[23][24][25][26]

Originally the station in Humen was to be named Dongguan but this was changed to Humen to avoid confusion with an existing Dongguan railway station on the Guangzhou–Shenzhen Railway in the town of Changping.

Hong Kong Section

edit

The Hong Kong section is in total 26 km (16 mi) of dedicated underground track, emergency rescue sidings and the stabling sidings in Shek Kong, ventilation facilities at Mai Po, Ngau Tam Mei and Pat Heung, along with an emergency access point at Tai Kong Po and eventually terminating at Hong Kong West Kowloon station.

The Regional Express Line originally envisaged in the Railway Development Strategy 2000 proposed by the Hong Kong Special Administrative Region Government (HKSAR Government), has now become the Hong Kong section of the Guangzhou–Shenzhen–Hong Kong Express Rail Link (XRL). In April 2008, the HKSAR Government asked the MTR Corporation to carry out further planning and design of the Express Rail Link. Subsequently, the HKSAR Government gazetted the Scheme for the Express Rail Link under the Railways Ordinance to collect public views.

In early 2009, the government of Hong Kong signed a memorandum of understanding with the Chinese Ministry of Railways that would permit the construction of the Shenzhen–Hong Kong section of the railway.[27]

On 20 October 2009, the Chief Executive in Council authorised the scheme and the Amendments of the Scheme of the Express Rail Link. On 16 January 2010, the Finance Committee of the Legislative Council approved the funding application for the construction of the Express Rail Link. The construction commenced in late January 2010[28] and was completed in September 2018.[29] In October 2014, an MTR report warned that the revised budget of HK$71.5 billion might be at risk.[30] This section had been expected to open in 2015, but severe storms flooded the tunnels and caused immense damage to the Tunnel Boring Machines in March 2014.[31] The railway has been expected to be completed in third quarter of 2018. According to the Rail Merger Bill, MTR Corporation will lease the rights to conduct operations on this line, until 1 December 2057.[32]

With the completion of the section, the journey time through the Rail Link have been reduced to 14 minutes between WKT and Futian stations, 23 minutes between Hong Kong and Shenzhen North and 48 minutes between Hong Kong and Guangzhou South. As of 2015, the cost of the project has risen substantially to HK$85.3 billion.[33]

Construction

edit
 
West Kowloon Terminus construction site
  • This commenced on 30 December 2004, in line with the overall commencement of the Wuhan-Guangzhou passenger line, building the new Guangzhou South station.
  • In September 2005, the National Development and Reform Commission officially approved the “Shenzhen-Hong Kong railway passenger line from Guangzhou to Shenzhen section Feasibility Study”.
  • On 18 December 2005, Guangzhou–Shenzhen–Hong Kong Express Rail Link's Guangzhou–Shenzhen section began formal construction.
  • In January 2010, construction commenced on the Hong Kong section.
  • In March 2011, Completion of the 10.8-km-long Shiziyang Tunnel to allow the railway to cross the Shiziyang Channel (Chinese: 狮子洋) of the Pearl River between the Dongchong and Humen Stations.[34][35]
  • On 26 December 2011, the Guangzhou–Shenzhen–Hong Kong Express Rail Guangzhou–Shenzhen section opened to Shenzhen North.
  • On 30 March 2014, Severe storm hits Hong Kong, flooding the tunnels and damaged the Tunnel Boring Machines. This has caused a 3-month delay to construction.
  • On 31 December 2014, The tunnel linking Shenzhen North station and Futian station was reported completed.[36] The construction of the tunnel, which runs about 10 kilometers, took about six years.
  • On 30 December 2015, Futian station commences intercity train operations.[29]

Operations

edit
 
Shenzhen North station east square

At present, Guangzhou–Shenzhen–Hong Kong Express Rail operates around 104 northbound trains and 101 southbound trains a day, three pairs of separate lines on weekends, a separate peak line 20 pairs and 7 high-speed sleeper train pairs, including:

  • Guangzhou South ↔ Chaoshan - 8 pairs, a separate peak line 2 pairs
  • Guangzhou South ↔ Shanghai Hongqiao - 3 high-speed sleeper train pairs
  • Guangzhou South → Shenzhen North - 17 trains, 3 weekend trains and a separate peak line 2 trains; Shenzhen North→Guangzhou South - 20 trains, 3 weekend trains and a separate peak line 2 trains
  • Guangzhou South ↔ Futian - 23 pairs, a separate peak line 4 pairs
  • Shenzhen North ↔ Guilin North - 3 pairs
  • Shenzhen North ↔ Guiyang North - 1 pair
  • Shenzhen North ↔ Nanning East - 3 pairs
  • Shenzhen North ↔ Yongzhou - 1 pair
  • Shenzhen North ↔ Changsha South - 12 pairs
  • Shenzhen North ↔ Shaoyang - 2 pairs
  • Shenzhen North ↔ Huaihua South - 4 pairs
  • Shenzhen North ↔ Nanchang West- 2 pairs
  • Shenzhen North ↔ Yueyang East - 1 pair
  • Wuhan ↔ Shenzhen North - 12 pairs
  • Yichang ↔ Shenzhen North - 1 pair
  • Shenzhen North ↔ Chongqing North - 1 pair
  • Shenzhen North ↔ Jinan West - 1 pair
  • Shenzhen North ↔ Luohe West - 1 pair
  • Shenzhen North ↔ Zhengzhou East - 2 pairs, 1 extra pair of during peaks
  • Shenzhen North ↔ Xi'an North - 3 pairs, a separate peak line one pair
  • Shenzhen North ↔ Shijiazhuang - 1 pair
  • Shenzhen North ↔ Beijing West - 2 pairs, 4 high-speed sleeper train pairs

In December 2014, overnight high-speed sleeper trains were added to several long-distance destinations, such as Beijing.

Stations

edit
Station Name Year Opened Transfer District City Pictures
English Simplified Chinese
(Traditional Chinese)
Guangzhou South (Guangzhounan) 广州南
(廣州南)
2010 Panyu Guangzhou  
Qingsheng 庆盛
(慶盛)
2011 Nansha  
Humen 虎门
(虎門)
Humen Dongguan  
Guangmingcheng 光明城
(光明城)
Bao'an Shenzhen  
Shenzhen North (Shenzhenbei) 深圳北
(深圳北)
Longhua  
Futian 福田
(福田)
2015 Futian  
Hong Kong
West Kowloon
香港西九龙
(香港西九龍)
2018 Yau Tsim Mong Hong Kong SAR  

Trains and equipment

edit
 
CRH380A EMU (CR version)
 
CR400AF-A EMU

The following is a list of operators using the line and their respective rolling stock :

Railway Group Rolling Stock
CR Guangzhou CRH2E, CRH3C, CRH380B, CR400AF, CR400AF-A
CR Shanghai CRH1E, CR400BF-A
CR Nanchang CRH380A
CR Wuhan CRH380AL, CRH380A
CR Zhengzhou CRH380AL
CR Xi'an CRH380AL, CRH380B
CR Beijing CR400AF, CRH380AL, CRH2E
MTR Vibrant Express (MTR CRH380A)

In Hong Kong, MTR announced their intention to purchase several high-speed EMUs. The tender (contract number: 840) was for 9 trainsets, each with 8 cars and a maximum operating speed of 350 km/h. Chinese manufacturer CSR Qingdao Sifang emerged as the successful bidder, based on the CRH380A "Harmony" model. The purchase contract was signed on 16 April 2012 at the headquarters of MTR.[37][38]

Tickets

edit

Train fare table G numbered trains (Business seat fare / VIP Class fare / First Class fare / Second Class fare; Unit: yuan; tickets for children, disabled veterans half price tickets, student tickets share a quarter discount of the fare for a Second Class ticket.)[39]

Guangzhou South
64.5 / 44.5 / 34.5 / 24.5 Qingsheng
99.5 / 59.5 / 49.5 / 34.5 39.5 / 24.5 / 19.5 / 14.5 Humen
169.5 / 99.5 / 84.5 / 59.5 104.5 / 64.5 / 54.5 / 40 64.5 / 44.5 / 34.5 / 24.5 Guangmingcheng
199.5 / 119.5 / 99.5 / 74.5 139.5 / 84.5 / 69.5 / 49.5 104.5 / 64.5 / 54.5 / 39.5 39.5 / 24.5 / 19.5 / 14.5 Shenzhen North
215 / 130 / 108 / 82 120 / 70 / 60 / 45 30 / na / 24 / 18 40 / 25 / 20 / 15 Futian
645 / 387 / 344 / 215 555 / 333 / 296 / 185 533 / 320 / 285 / 178 284 / 171 / 152 / 95 226 / 136 / 120 / 75 204 / 122 / 109 / 68 West Kowloon

Accidents and incidents

edit
  • At 6:30 on 18 February 2012, power supply equipment failure, resulting in train delays.[40]
  • On 26 September 2018, an inbound CR400BF-A trainset was unable to completely open one of its doors at West Kowloon station, as the platform edge exceeded the track's structure gauge. The train was redirected to platform 6. No casualties or injuries were reported. As a result, MTR stated that they were working with mainland authorities to investigate and address the issue and that all inbound CR400BF-A trains were to only use platform 6 until the problem was eliminated.[41]

See also

edit

References

edit
  1. ^ a b 阮, 文忠. 广深港高速铁路深港跨境隧道之设计与施工管理 [Guangzhou-Shenzhen-Hong Kong High Speed Rail Cross-border Tunnel Design and Construction Management] (PDF) (Report) (in Simplified Chinese). China Hong Kong Railway Institution. Retrieved 2022-08-15. "深圳福田站至深圳河线路全长 11.4km,设计速度目标值 200km/h [...] 香港段全长约 26km,设计速度目标 200km/h
  2. ^ Legislative Council Panel on Transport Subcommittee on Matters Relating to Railways. Latest update on issues relating to train of the Hong Kong Section of the Guangzhou-Shenzhen-Hong Kong Express Rail Link (PDF) (Report). Legislative Council of Hong Kong. June 2016. Retrieved 2022-08-15.
  3. ^ "Hong Kong's first high-speed train makes maiden trip across border, as Carrie Lam says rail link will be 'bright light' on China's calling card". SCMP. Retrieved 22 September 2018.
  4. ^ "Hong Kong Opens High-Speed Rail Link With Mainland China, Makes Maiden Trip Across Border". Headlines Today. Retrieved 22 September 2018.
  5. ^ "Guangzhou-Shenzhen-Hong Kong Express Rail Link Opens To Public". Headlines Today. Retrieved 23 September 2018.
  6. ^ Chan, Fung (2020). "The Guangdong–Hong Kong–Macao Greater Bay Area: Enhancing collaborative governance of the CEPA implementation and regional integration". China: An International Journal. 18 (1): 171–191. doi:10.1353/chn.2020.0011.
  7. ^ "立法会参考资料摘要:铁路发展策略" (PDF). Legislative Council of Hong Kong. 2000-05-16. Retrieved 2011-03-06.
  8. ^ "广深港高速走东站还是番禺?". 金羊网. 2002-09-22. Archived from the original on 2012-12-07. Retrieved 2011-03-06.
  9. ^ "鐵路發展策略2000" (PDF). Transport and Housing Bureau, Government of Hong Kong. May 2000. Archived from the original (PDF) on 2007-03-17. Retrieved 2011-03-06.
  10. ^ "香港研究在京港线、沪港线开通磁悬浮列车". 中新网. 2001-08-16. Archived from the original on 2020-05-10. Retrieved 2011-03-06.
  11. ^ "磁 浮 列 車 一 小 時 內 抵 廣 州". Sing Tao Daily. 2001-09-29. Retrieved 2011-03-06.[permanent dead link]
  12. ^ "新闻公报:政務司司長談話全文". 香港特别行政区新闻署. 2001-09-29. Retrieved 2011-03-06.
  13. ^ "穗深港间建磁浮列车? 铁道部称视沪样板表现". 东方网. 2003-01-03. Archived from the original on 2020-11-03. Retrieved 2011-03-06.
  14. ^ 孙静惟 (2002-01-01). "港深穗研建高速铁路". 大公报.
  15. ^ "港粵合作進入更高層次". 文汇报. 2002-02-02. Retrieved 2011-03-06.
  16. ^ "广深港间拟建区域快线 可能采用磁悬浮列车". 新华网. 2002-02-01. Archived from the original on December 18, 2002. Retrieved 2011-03-06.
  17. ^ "立法会内务委员会 特别会议纪要" (PDF). Legislative Council of Hong Kong. 2002-04-19. Retrieved 2011-03-06.
  18. ^ "立法会十题:广深港高速铁路规划中". Transport and Housing Bureau, Government of Hong Kong. 2004-11-10. Retrieved 2011-03-06.
  19. ^ "财务委员会审核二OO四至O五年度开支预算 管制人员的答覆" (PDF). Legislative Council of Hong Kong. 2004-05-23. Retrieved 2011-03-25.
  20. ^ "新闻公报:政务司司长促进内地与香港基建合作". 香港特别行政区政府新闻署. 2002-09-20. Retrieved 2011-03-06.
  21. ^ 广深港高速铁路倾向于轮轨 40分钟广州到香港. Guangzhou Daily. 2003-08-07. Retrieved 2011-03-06.
  22. ^ Yang Fanglong (杨芳龙) (2010). 地下高铁站广深港客运专线深圳福田站设计. 《山西建筑》 (9).
  23. ^ 廣深港高速鐵路正式拍板 香港到深圳只需14分鐘. Archived from the original on 2010-03-12. Retrieved 2014-12-31.
  24. ^ 广深港专线光明站施工 至中心区将仅10分钟. Archived from the original on 2010-06-06. Retrieved 2014-12-31.
  25. ^ 广深港高铁全长142公里 龙华到达香港只需14分钟. 在广州南站候車廳展示的广州鐵路樞紐總平面布置示意圖,明確標出东涌站及光明站為廣深客運專線(即本線路)車站
  26. ^ Xiong Wei (熊薇); Xu Xiaolei (许晓蕾); Ma Qiang (马强) (2011-07-25). 广深港高铁开通在即 "东涌站"更名"庆盛站". 南方都市报. Archived from the original on 2012-01-14. Retrieved 2011-07-25.
  27. ^ "Hong Kong Express Rail Link agreement signed". International Railway Journal. 1 April 2009. Archived from the original on 19 March 2016. Retrieved 1 May 2015 – via HighBeam Research.
  28. ^ "High speed rail link project delayed". RTHK. 16 April 2014.
  29. ^ a b "Asia's largest underground railway station opens for business". London: Smart Rail World. January 5, 2016. Retrieved January 6, 2016.
  30. ^ "Report to the Independent Board Committee on the Hong Kong Express Rail Link Project", MTR, Hong Kong, pp. A1–A122. Flyvbjerg, Bent and Kao, Tsung-Chung and Budzier, Alexander, October 28, 2014.
  31. ^ "Damaged TBM Delays Hong Kong to Guangzhou Rail Link". Break Bulk. 2014-04-17. Retrieved 2014-12-31.[permanent dead link]
  32. ^ 立法會參考資料摘要:廣深港高速鐵路香港段(第11至16段)22 April 2008, Transport and Housing Bureau, Government of Hong Kong.
  33. ^ "Key Information". Express Rail Link. MTR Corporation. Archived from the original on 15 October 2010. Retrieved 11 August 2015.
  34. ^ "China starts work on first underwater railway tunnel_Sci&Tech—China Economic Net". en.ce.cn. Archived from the original on 2012-02-12. Retrieved 2014-03-11.
  35. ^ China completes construction of world's fastest underwater railway tunnel, Xinhua News Agency, 2011-03-12
  36. ^ "Tunnel Completed". Shenzhen Daily. Archived from the original on 31 December 2014. Retrieved 31 December 2014.
  37. ^ "中国南车获香港高铁13.6亿元订单" [CSR received 1.36 billion orders from Hong Kong high-speed rail] (Press release) (in Simplified Chinese). CSR. 2012-04-18. Archived from the original on 2012-12-15.
  38. ^ "中国南车中标香港高铁列车合约" [CSR wins the bid for the Hong Kong high-speed rail train contract] (Press release) (in Simplified Chinese). CSR. 2014-12-31. Archived from the original on 2014-12-31.
  39. ^ "rmb-implemented-fare-chart". MTR. Retrieved 4 July 2024.
  40. ^ "广深港高铁供电设备故障 多趟车晚点". Archived from the original on 2020-08-07. Retrieved 2014-12-31.
  41. ^ Zhuang, Gongnan (2018-09-27). "高鐵又甩轆?譚文豪:8號月台疑設計缺陷 有列車無法正常開門". hk01.com (in Traditional Chinese). Retrieved 2018-09-30.
edit