The Airport Link is a tunnelled, motorway grade, toll road in the northern suburbs of Brisbane, Queensland, Australia. It connects the Brisbane central business district and the Clem Jones Tunnel to the East–West Arterial Road which leads to the Brisbane Airport. It was built in conjunction with the Windsor to Kedron section of the Northern Busway in approximately the same corridor.
Airport Link | |
---|---|
Heading northbound toward Southern Portal from Fortitude Valley on ramp (Preview Walk) | |
General information | |
Type | Motorway |
Length | 6.7 km (4.2 mi) |
Opened | 2012 |
Major junctions | |
South end | Inner City Bypass, Bowen Hills |
Gympie Road Stafford Road | |
North-east end | Gateway Motorway East–West Arterial Road |
Location(s) | |
Major suburbs / towns | Windsor, Lutwyche, Kedron, Wooloowin |
Highway system | |
The Airport Link and busway project involves 15 kilometres (9.3 mi) of tunnelling including the road (6.7 km of twin tunnels), busway tunnels and connecting ramps, as well as 25 bridges and result in over 7 kilometres (4.3 mi) of new road. The Airport Link was Australia's longest road tunnel until the opening of the M8 in Sydney.
The estimated construction cost of the Airport Link is $4.8 billion.[1] The toll for the full length is $6.38 for a car.[2]
Construction of the Airport Link, Northern Busway and Airport Roundabout Upgrade projects were scheduled for completion in mid-2012.[3] Following a preview walk on 15 July 2012 and final safety approvals, the Airport Link opened to the public at 11.55 pm on 24 July 2012.[4]
Contract and controversy
editThe contract was awarded to the consortium BrisConnections, composed of Macquarie Group, Thiess and John Holland, beating two other consortia (North Connect and Northern Motorway). BrisConnections was announced as the preferred bidder on 19 May 2008,[5] and the final contract was awarded on 2 June 2008.
Conducted as a public-private partnership (PPP), the financial aspects of the Airport Link project has been mired in controversy from the outset. Macquarie Group charged $110 million in fees for the financial engineering which used the equity from private investors to raise the necessary debt and planned to pay investor distributions from capital, an arrangement which resembles a Ponzi scheme and has been ridiculed as the "dead parrot model", after the famous Monty Python comedy sketch.[6] Former Queensland Premier Anna Bligh enjoyed a free holiday at the Sydney mansion of Thiess director Ros Kelly just before the contract was awarded.[7] Former Labor ministers Terry Mackenroth and Con Sciacca were paid a "success fee", (as government relations advisors) believed to be about $500,000, by BrisConnections after the consortium won the tender.[8]
BrisConnections was listed as a unit trust on the Australian Securities Exchange (ASX) via a $1.2 billion initial public offering (IPO) of installment receipts (or stapled securities) on 31 July 2008 (ASX: BCS). This was the largest IPO in Australia in 2008 and the most disastrous. The value of initial $1 installments fell by 60 per cent on the first day of trading, and by late November had collapsed to 0.1c, the lowest possible price on the ASX.[9] The dramatic price slide was largely due to the leverage risk associated with stapled securities.[10] Among the institutional investors was the Queensland Investment Corporation (QIC), which invested $25 million. The chairman of QIC is Trevor Rowe, who is also the Chairman of BrisConnections and was awarded Member of the Order of Australia in 2004 "for service to the investment banking sector and as a contributor to the formulation of public policy ... and to the community."[11]
It is believed that some of this negative market sentiment was in response to the traffic forecasts contained within the Product Disclosure Statement lodged by BrisConnections. The EIS previously lodged by government showed traffic forecasts in 2012 of 95,000 vehicles per day, rising to 120,000 motorists by 2026. The Product Disclosure Statement prepared by PBA provides forecast of 193,000 vehicles in 2012 rising to 291,000 vehicles by 2026.
During the early period of the BrisConnections listing most of the securities were owned by institutional investors, however as the price collapsed many of these institutions divested their now worthless stock, including Macquarie Group.[12] Most of these shares were taken up by retail investors who were unaware that two further $1 installments on the stapled securities were owing and faced financial ruin as a result.[13] BrisConnections has threatened to sue these investors in order to raise the capital necessary to continue the project, while reducing dividends by 99 per cent.[14] There are no further installments owning which means there are no further obligations on shareholders attached to the units.[15]
While promoting BrisConnections at their media event in April 2009, Premier Anna Bligh denied any responsibility for the fate of the "Mum and Dad" investors saying, "it is not the role of the Queensland Government to underwrite private investment decisions made by people who were seeking to make a profit investing in the stock market".[16] At this time, the Australian Securities and Investments Commission (ASIC) belatedly sought to act on behalf of investors and to seek an independent report of BrisConnections' finances.[17] BrisConnections was nearly wound up in April 2009 after the private company of one investor, Nicholas Bolton, requisitioned a general meeting of members of the managing company. However, on the date of the meeting the proxies attached to Bolton's shares were exercised to against the resolutions, Bolton's company having earlier sold the proxy rights for $4.5 million to Thiess-John Holland Group and the contractor for the Airport Link project. Therefore, the special resolution fell short of the required 75% vote to pass and BrisConnections was allowed to continue operating under its current form.[18]
In May[when?], 70% (278 million) of outstanding shares defaulted on the second $1 instalment payment.[19] Some shareholders transferred their shares off market to false identities, such as Humphrey B. Bear, in order to avoid payment.[20] An auction of shares in default failed to attract a bidder. In June, BrisConnections commenced legal action to recover the unpaid moneys. With Brisconnections launching legal claims against defaulting investors, controversial businessman Jim Byrnes postured as a champion of small investors.[21] The controversy featured prominently in Brisbane newspapers: The name 'BrisConnections' was played upon as a 'con', the project and ensuing farce being dubbed by the media as 'BrisCon'. In October, BrisConnections notified ASX it would stop pursuing defaulting investors.[22]
By early December 2009, the share price of the second $1 installments had collapsed to 0.1c. With little other interest in the "toxic" stock at this time, the chief executive officer, Ray Wilson, paid $10 for 5,000 shares.[23] Two other directors of BrisConnections also purchased share parcels of a similar size, helping to raise the share price to 0.5c by mid-December, however the share price had again collapsed to 0.1c by year's end.
On 13 November 2012, BrisConnections was suspended from trading indefinitely, to pursue talks with lenders.[24] On 19 February 2013, BrisConnections go into voluntary administration owing more than the value of the asset[25] The board called in McGrathNicol as administrators and PPB Advisory as receivers for the $3.5 billion debt owed to a syndicate of banks led by ANZ.[26] Other banks in the syndicate include: BNP Paribas, United Overseas Bank, KBC Finance Ireland, Societe Generale, UniCredit, BOS International, Depfa Bank, DZ Bank, and Allied Irish Banks.
In November 2015, Transurban Queensland (of which Transurban owns 62.5%) announced the acquisition of BrisConnections and AirportlinkM7.[27] The acquisition was finalised in April 2016.[28]
Construction
editThe tunnel opened to the public at 11.55 pm on Tuesday, 24 July 2012.[4]
Milestones
edit- 19 May 2008 – State government announced BrisConnections as the preferred bidder for Airport Link
- November 2008 – Official start to project construction
- December 2008 – Drill and blast excavation commenced at Bowen Hills, construction of cut and cover structure at Toombul (Kalinga Park) commences
- March 2009 – First roadheader commenced tunnelling at Truro Street site (mid tunnel point) in Windsor
- April 2009 – Roadheader tunnelling commenced at Federation Street site in Bowen Hills
- May 2009 – 24-hour tunnelling operations commence across the project
- June 2009 – Roadheader tunnelling commences in Kedron
- November 2009 – First Tunnel boring machine (TBM) arrives from Germany for assembly
- March 2010 – Completion of both cut and cover structure and Tunnel Boring Machine (TBM) launch box at Toombul,[3] 3.3 kilometres (2.1 mi) of tunnels were already dug and 13 roadheader machines (each 18.2 m in diameter and weigh ) in use on tunnels. In the months that followed this rose to 16 roadheader machines.[1]
- 18 June 2010 – First mined tunnel breakthrough between Bowen Hills and Lutwyche. Transport Minister Rachael Nolan witnessed the occasion.
- Mid 2010 – First TBM commences tunnelling from Toombul while second TBM arrives from Germany
- Mid 2010 – Second TBM commences tunnelling from Toombul heading west toward Lutwyche
- Early 2011 – Northern Busway tunnelling complete
- Early 2011 – TBMs removed from tunnel shaft at Chalk Street in Lutwyche
- Late 2011 – Airport Roundabout Upgrade complete
- 15 July 2012 – Construction complete and public preview walk
- 24 July 2012, 11.55 pm – Airport Link opens to public after final safety certification[4]
History
editOn 17 June 2009, CNI requested that the Coordinator-General evaluate a proposed change to the Airport Link project under section 35C of the State Development and Public Works Organisation Act 1971. Due to the discovery during the first half of 2009 of less than favourable ground conditions in the vicinity of the Kedron ramps, BrisConnections proposed the establishment of a new worksite on vacant land at Rose Street, Wooloowin, between Kent and Park Roads to facilitate improved construction access to the mainline tunnels. A shaft 15 metres in diameter and 42 metres deep would be constructed to launch two of the project’s ‘roadheader’ excavation machines. It is anticipated that the worksite would be in use for up to 29 months, including backfilling and rehabilitation.
In August 2009 the main earthmoving contractor TF Group went into receivership, owing subcontractors as much as $2.8 million. A group of these subcontractors threatened to blockade the project until their outstanding debts were paid.[29]
On 15 July 2012, the tunnel was opened to registered visitors for a preview walk[30] named the "Bridge and Tunnel Experience".
Tolls
editIt was estimated the toll charge per trip would be $4.90 for the entire length between Bowen Hills and Toombul, and $3.75 between Kedron and Toombul, when full tolling commenced in November 2013.[31] These tolls were set at $4.00 and $3.00 respectively in 2006 and are being increased in line with Brisbane CPI.[32]
The tolls were phased in between July 2012 and November 2013, with an initial one-month toll free period for all users, a further 2 months toll-free for account holders, then followed by introductory tolls.
The tolls are collected via a 'free-flow tolling system', an electronic tolling system based on overhead gantries reading a tag fitted inside vehicles or by taking a photograph of number plates, avoiding the need for vehicles to slow or stop. Motocycles do not need a tag and do not incur a number-plate matching fee. The Linkt system is used. Any other Australian toll road tag will work on the Airport Link toll road.[32]
The motorway has 2 sets of gantries, one set at the southern and another at the northern end. Vehicles entering or exiting midway at Kedron to or from Toombul will therefore only pass one gantry and will pay a partial toll. Vehicles passing both sets of gantries are charged the full toll.[33]
Toll road | Class 1 (Motorcycles) | Class 2 (Cars) | Class 3 (Light Commercial Vehicles) | Class 4 (Heavy Commercial Vehicles) | Toll increase | Toll concessionaire[35] | Expiry of toll concession[36][37]
| |
---|---|---|---|---|---|---|---|---|
AirportlinkM7 | Bowen Hills to Kedron or Toombul | $3.36 | $6.72 | $10.08 | $17.79 | Annually on 1 January, by CPI | Transurban Queensland[a] (62.5% owned by Transurban) |
July 2053 |
Kedron to Toombul | $2.52 | $5.03 | $7.55 | $13.35 | Annually on 1 January, by CPI
|
Patronage
editTraffic forecaster Arup, acting for BrisConnections, had predicted 135,000 vehicles a day will use the road one month after its opening. They forecast that it would climb to 160,000 vehicles per day by July 2015 and 291,000 vehicles per day by 2026.[38] However another forecaster, Veitch Lister Consulting, estimated that traffic would rise to 91,600 vehicles per day by October 2012 but would fall to 70,300 by April 2013 when introductory tolls are introduced and to 53,900 after November 2013 when the full toll becomes effective.[39]
During its first week of operation the tunnel was used by an average 77,320 vehicles each day.[40]
The toll road remained free during its ramp up phase. Average daily patronage for August 2012 was 81,470, with average weekday traffic of 85,862.[41] This has led some analysts to conclude that its days as a publicly listed company are limited.[42] In February 2013, when Airport Link went into receivership, the average daily traffic using the road was 47,802 vehicles.[43]
Safety
editBrisconnections, the operator of the tunnel, claim the tunnel is the safest in Australia.[44] A speed limit of 80 km/h along the main tunnel motorway and 60 km/h on exit and entry ramps has been set. Variable message signs 120 metres apart within the tunnel are used to convey important information. Six fixed speed cameras in 10 possible locations are in operation. There are 500 CCTV cameras, which can be viewed on 46 individually controlled monitors in the control room.[44] An underground loudspeaker system is available if needed. Micro-heat detectors are able to measure temperature every six minutes and fire sprinklers that can deliver 600 millimetres an hour of water, are claimed to be able to put out a major fire in minutes.[44] There is a 24-hour control room at Kedron with two operators and a supervisor.[44]
A smoke duct, is present throughout the entire length of the tunnel and 6 ventilation fan (300hp each) can blow the smoke out of the tunnel with a very quick response time blowing full power.
See also
editNotes
edit- ^ a b The Honourable Stirling Hinchliffe (19 March 2010). "Tunnelling Underway on Airport Link and Northern Busway (Windsor to Kedron)". Ministerial Media Statements. The State of Queensland (Department of the Premier and Cabinet). Archived from the original on 16 July 2011. Retrieved 19 March 2010.
- ^ "AirportLinkM7 toll price changes from 1 January 2023". Archived from the original on 9 November 2023. Retrieved 30 October 2023.
- ^ a b BrisConnections (2009). "Construction". Airport Link and Northern Busway website. BrisConnections. Archived from the original on 13 November 2009. Retrieved 19 March 2010.
- ^ a b c "Drivers queue to be first through Airport Link". Brisbane Times. Fairfax Media. 25 July 2012. Archived from the original on 26 July 2012. Retrieved 26 July 2012.
- ^ CityNorth Infrastructure, Delivering the Projects Archived 2 April 2012 at the Wayback Machine. Retrieved 10 September 2011.
- ^ Michael West (31 July 2008)Macquarie's dead parrot model Archived 6 August 2016 at the Wayback Machine. Business Day.
- ^ Patrick Lion and Steven Wardill. (17 July 2008).Anna Bligh fails to declare free holiday in Sydney mansion Archived 21 April 2009 at the Wayback Machine. Courier-Mail.
- ^ Steven Wardill (23 January 2009). Terry Mackenroth, Con Sciacca share fee on airport link contract Archived 21 April 2009 at the Wayback Machine. Courier-Mail.
- ^ Google Finance, BrisConnections Unit Trusts Archived 26 February 2018 at the Wayback Machine
- ^ Bryan Frith (3 April 2009). Leverage loss turns BrisCon toll road into a goat track. The Australian. Retrieved 21 February 2013
- ^ Search Australian Honours Archived 26 May 2011 at the Wayback Machine It's an Honour. Australian Government.
- ^ Business Spectator, "Macquarie Investment sells 9m BrisConnections units", Business Spectator, 23 October 2008 Archived 26 April 2009 at the Wayback Machine
- ^ The 7.30 Report, "Many BrisConnections shareholders facing financial ruin", ABC Television, 20 November 2008 Archived 23 February 2009 at the Wayback Machine
- ^ Jacob Saulwick, "Woes mount for toll road", Sydney Morning Herald, 31 October 2008 Archived 13 November 2008 at the Wayback Machine
- ^ Mark Hawthorne (30 January 2009) Peering deep into a long, dark tunnel Archived 27 March 2009 at the Wayback Machine. BusinessDay. Retrieved 21 February 2013.
- ^ (24 April 2009) Class action filed against BrisConnections Archived 28 November 2009 at the Wayback Machine. PM - ABC Local Radio.
- ^ Mark Hawthorne (3 April 2009). BrisConnections in check Archived 25 November 2009 at the Wayback Machine. The Age.
- ^ Mark Hawthorne (15 April 2009). Bolton sells his BrisCon voting rights for $4.5m Archived 17 April 2009 at the Wayback Machine. Sydney Morning Herald. Retrieved 21 February 2013.
- ^ Richard Gluyas (6 June 2009). "BrisCon securities auction fails to get a single bid". The Australian. Archived from the original on 13 September 2012. Retrieved 16 December 2011.
- ^ Hawthorne, M (17 April 2009). "Calling Humphrey Bear, please come in". The Age. Archived from the original on 27 June 2009. Retrieved 14 June 2009.
- ^ Danny John (29 June 2009). "Byrnes in spotlight over BrisConnections". The Age. Archived from the original on 27 January 2010. Retrieved 1 April 2010.
- ^ Brisconnections investors spared liabilities Archived 12 December 2009 at the Wayback Machine. 17 October 2009.
- ^ This road is a boulevard of broken dreams Archived 29 December 2009 at the Wayback Machine. Mark Hawthorne. Business Day. 11 December 2009.
- ^ "BrisConnections shares suspended indefinitely - ABC News (Australian Broadcasting Corporation)". Australian Broadcasting Corporation. 12 November 2012. Archived from the original on 24 August 2014. Retrieved 15 September 2015.
- ^ Robyn Ironside (19 February 2013). BrisConnections, operators of Brisbane Airport Link, go into voluntary administration Archived 19 February 2013 at the Wayback Machine. The Courier-Mail. Retrieved 21 February 2013.
- ^ "BrisConnections calls in receivers as banks reject revamp plan | the Australian". Archived from the original on 20 February 2013. Retrieved 15 September 2015.
- ^ "Transurban acquires BrisConnections for up to $2 billion". Australian Financial Review. 24 November 2015. Archived from the original on 1 February 2016.
- ^ "Transurban announces financial close on AirportlinkM7" (PDF). ASX. Transurban. 4 May 2016. Archived (PDF) from the original on 1 June 2016.
- ^ Mark Solomons (22 August 2009). Truckies threaten road block. Courier-Mail. Queensland Newspapers.
- ^ "Test walk the new Airport Link tunnel". Brisbane Times. Fairfax Media. 15 July 2012. Retrieved 15 July 2012.[permanent dead link ]
- ^ Tony Moore (25 July 2012). "How to use Airport Link". Brisbane Times. Fairfax Media. Archived from the original on 26 August 2012. Retrieved 26 July 2012.
- ^ a b BrisConnections (2009). "FAQs - Investing in BrisConnections". Airport Link and Northern Busway website. BrisConnections. Archived from the original on 30 September 2009. Retrieved 19 March 2010.
- ^ "Toll Information". AirportLink M7. BrisConnections. 2012. Archived from the original on 22 July 2012. Retrieved 25 July 2012.
- ^ "Toll pricing". Linkt. Retrieved 9 January 2024.
- ^ "Toll roads". Department of Transport and Main Roads. 10 April 2016. Retrieved 15 October 2021.
- ^ "Brisbane". Transurban. Retrieved 15 October 2021.
- ^ "Transurban Queensland Euro Medium Term Note Programme Update" (PDF). 31 October 2016. p. 9. Retrieved 18 October 2021.
- ^ "Airport Link will 'miss forecasts'". Brisbane Times. Fairfax Media. 29 June 2012. Archived from the original on 26 March 2014. Retrieved 24 July 2012.
- ^ "Zenith Airport Link Forecasts – Update". VLC. 12 November 2012. Archived from the original on 2 June 2021. Retrieved 31 May 2021.
- ^ Robyn Ironside (2 August 2012). "Brisbane's Airport Link reveals patronage figures for first week". Herald Sun. The Herald & Weekly Times. Retrieved 2 August 2012.
- ^ "ASX Release AirportLink M7 Traffic" (PDF). Brisconnections. 3 September 2012. Archived (PDF) from the original on 24 December 2012. Retrieved 14 September 2012.
- ^ "Brisconnect to join RiverCity in toll road graveyard". Bristlemouth. 7 September 2012. Archived from the original on 2 November 2012. Retrieved 14 September 2012.
- ^ Tony Moore (21 February 2013). "Clem7 tunnel forecasts back in court". Brisbane Times. Fairfax Media. Archived from the original on 22 February 2013. Retrieved 21 February 2013.
- ^ a b c d Tony Moore (19 July 2012). "Airport Link 'Australia's safest tunnel'". Brisbane Times. Fairfax Media. Archived from the original on 21 July 2012. Retrieved 26 July 2012.
External links
edit- Official site
- BCC project site
- TransLink project site for Northern Busway
- Forum - AirportLink Forum
27°24′36.76″S 153°03′19.73″E / 27.4102111°S 153.0554806°E